Summary: |
Finding and Order that by March 8, 2017, NS filed notice that it has initiated with AEP or any other applicable utility the process to ensure that electric service will be available at the involved grade crossing as set forth in paragraph 8 and that NS follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by November 8, 2017. |
|