Summary: |
Finding and ordered, That by February 9, 2019, CSX file notice that it has initiated with CEI, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossing as set forth in Paragraph 8. It is, further, That CSX follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by January 9,2020. |
|