Summary: |
Finding & Order stating that by April 5, 2013, I&O file a notice that they have initiated with AEP, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossing as set forth in finding 3; that I&O follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by December 6, 2013 and notify the Commission and ORDC 30 days before the projected date of completion, to notify Staff at least five working days before the date work is scheduled to begin at the project site so that arrangements can be made for any inspection and notify Staff of any change. |
|