Summary: |
Finding and order ordered that within 30 days of the issuance of this finding and order, W&LE shall file in the docket notice that it has initiated discussions with American Electric Power (AEP); that the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by October 23, 2012; that W&LE notify staff at least five working days before the
date work is scheduled to begin at the project site so that arrangements can be
made for inspections that W&LE timely notify staff of any changes in the scope of work, cost overruns, materials, etc., which are not in the approved plans and estimates, and shall secure approval before the work is performed. |
|