Summary: |
Entry ordering that CFE, NS, and CSX each submit to the Commission and ORDC site plans and cost estimates for projects by December 29, 2009; by January 5, 2010. CFE, NS, and CSX each file a notice advising that it has been submitted; by January 28, 2010, each file a notice that it has initiated with the applicable public utility the process to ensure electric service will be available; notify Commission and ORDC 30 days before the projected date of completion. |
|