Summary: |
Finding and order, that, by February 3, 2012, CSX file a notice that it has initiated with AEP the process to ensure that electric service will be available at the involved grade crossing as set forth in finding 3; that CSX follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by October 4, 2012. |
|