Summary: |
Finding and order ordered that by February 27, 2015, CSX file notice that it has initiated with
AEP, or any applicable utility, the process to ensure that electric service will be
available at the involved grade crossing, ordered that CSX follow the detailed instructions as outlined in the ORDC
letter of construction authorization and proceed with and complete the project by
October 28, 2015, ordered that CSX notify Staff at least five working days before the date work
is scheduled to begin at the project site so that arrangements can be made for any
inspection, ordered that CSX timely notify Staff of any changes in the scope of work,
cost overrun, materials, etc., which are not in the approved plans and estimates, and
shall secure approval before the work is performed, ordered that CSX notify the Commission and ORDC 30 days before the
projected date of completion, ordered that at the time Staff or ORDC makes its final inspection and finds
that the installation at the grade crossing is complete and the warning devices have
been put in service. Staff will file a memorandum in this docket indicating that the
installation is complete and the warning devices have been put in service. |
|