Summary: |
Finding and order ordered that Within 30 days of the issuance of this Finding and Order, CCRL shall file
notice that it has initiated discussions with Cleveland Electric Illuminating Company
(CEI) or any other applicable utility, to ensure that electric service will be available to
enable the grade crossing improvements to be constructed and placed in service within the deadline specified by the Commission. Such filing shall identify the steps CCRL has taken
with CEI, or any other electric utility, and the local highway authority to have electric
service available during the construction and cut-in phases of the project. |
|