Date Filed:  3/11/2020 5:33:47 PM View Document
Document Type:  NO-Notice View Document
Link to Document:  View Document
Number of pages:  1
Case Numbers: 
19-0802-EL-BNR
Summary: 
Notice stating that construction on Lordstown-Sammis 345 kV Loop to Wellsville Substation Project was completed on March 6, 2020 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.