Summary: |
Finding and order stating that by May 23, 2014, NS file a notice that it has initiated with Duke, BREB, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossings as set forth in finding (6); projects should be completed by January 23, 2015 and NS must notify staff at least 5 working days before the date work is scheduled to begin at the project sites so arrangements can be made for any inspection. |
|