Summary: |
Finding & Order stating that by July 20, 2012, NS file a notice that it has initiated with TE or any other applicable utility, the process to ensure that electric service will be available at the involved grade crossing as set forth in finding 3; that NS complete the project by March 20, 2013; that NS notify the Commission and ORDC 30 days before the projected date of completion and Staff or ORDC makes its final inspection and Staff file a memorandum that the installation is completed and the warning devices have been put in service. |
|