DIS - Cases with Industry Code EL ELECTRIC, Purpose Code BNR Construction notification report and Status CL CLOSED (72%20cases) Skip to main content

Cases with Industry Code "EL" ELECTRIC,
Purpose Code "BNR" Construction notification report,
and Status "CL" CLOSED (72%20cases)

Case NumberCase TitleOpen DateClosed Date
06-0654-EL-BNRAMERICAN TRANSMISSION SYSTEMS, INC/SEVILLE-WEST MEDINA 138kV TRANSMISSION LINE05/04/200611/13/2006
09-0568-EL-BNRAMERICAN TRANSMISSION SYSTEMS INCORPORATED/ MIDWAY-OI LEVIS 138KV TRANSMISSION LINE RELOCATION FOR ROACHTON ROAD WIDENING07/06/200903/20/2015
09-0621-EL-BNRFIRST SOLAR LLC NEW 138 KV SERVICE DELIVERY07/23/200903/20/2015
09-0779-EL-BNRTHE DAYTON POWER AND LIGHT COMPANY09/04/200903/20/2015
09-1914-EL-BNRAMERICAN TRANSMISSION SYSTEMS INC/BABB-EAST AKRON 138 KV TRANSMISSION LINE RELOCATION FOR THE MARTHA AVENUE ROUNDABOUT12/04/200903/20/2015
10-0125-EL-BNRJACKMAN WESTGATE 138 KV TRANSMISSION LINE POLE RELOCATION FOR SECOR ROAD WIDENING02/03/201003/20/2015
10-0389-EL-BNREASTLAKE SUBSTATION-EASTLAKE PLANT 138 KV SUPPLY PROJECT03/30/201003/20/2015
10-0423-EL-BNREDGEWATER SUBSTATION 138 KV SUBSTATION STRAIN BUS RELOCATION PROJECT04/01/201003/20/2015
10-0789-EL-BNRDUKE ENERGY OHIO INC/HUSTON 138KV ELECTRIC TRANSMISSION LINE LOOP06/08/201003/20/2015
10-1320-EL-BNRAMERICAN TRANSMISSION SYSTEMS INC09/03/201003/20/2015
10-1452-EL-BNRPLEASANT VALLEY WEST AKRON WEST 138 KV TRANSMISSION LINE TAP TO CLEVELAND CLINIC DATA CENTER SUBSTATION PROJECT09/30/201003/20/2015
10-3100-EL-BNRDUKE ENERGY OHIO/RED BANK 138 KV ELECTRIC TRANSMISSION LINE RELOCATION12/21/201003/20/2015
11-0488-EL-BNRCONSTRUCTION NOTIFICATION / LIMA- FORT WAYNE 138KV LINE TAP STRUCTURES / REQUEST FOR EXPEDITED TREATMENT01/31/201103/20/2015
11-0888-EL-BNRConstruction Notification (Maddox Creek Statopm Tap Structures02/24/201103/20/2015
11-4375-EL-BNRHANNA SUBSTATION EXPANSION PROJECT07/19/201103/20/2015
11-4376-EL-BNRSTAR SUBSTATION EXPANSION PROJECT07/19/201103/20/2015
11-4387-EL-BNROTTAWA-LAKEVIEW 138 KV TRANSMISSION LINE RECONDUCTORING PROJECT07/20/201103/20/2015
11-4388-EL-BNRHillsboro Maysville 138KV Line07/20/201103/20/2015
11-4655-EL-BNRIn the matter of a Construction Notice for the Poston - Ross 138kV Line Reconductor/Rebuild Project Submitted by American Electric Power08/05/201111/28/2011
11-4896-EL-BNRPoston - Ross 138k V Line Reconductor/Rebuild Section 108/26/201103/20/2015
11-5513-EL-BNRPOSTON/HARRISON 138KV LINE10/19/201103/20/2015
11-5582-EL-BNRGREENFIELD/LAKEVIEW 138 KV TRANSMISSION LINE RECONDUCTORING PROJECT11/01/201103/20/2015
11-5871-EL-BNRAMERICAN TRANSMISSION SYSTEMS INCORPORATED 12/07/201103/20/2015
11-6031-EL-BNRAMERICAN TRANSMISSION SYSTEMS INC. / JOHNSON-LORAIN 138 KV TRANSMISSION LINE RECONDUCTORING PROJECT12/23/201103/20/2015
12-0472-EL-BNRMarysville Station Expansion01/27/201203/20/2015
12-0706-EL-BNRPoston-Ross 138k V Line (Reconductor/Rebuild Project Section III)02/21/201203/20/2015
12-0833-EL-BNRHanging Rock Station Expansion03/02/201203/20/2015
12-0880-EL-BNRCHRYSLER-LEVIS PARK 138 KV TAP TO FIVE POINT SUBSTATION POLE RELOCATION AT STATE ROUTE 25 AND FIVE POINT ROAD03/08/201203/20/2015
12-1026-EL-BNRSouthwest Lima Station Expansion03/19/201203/20/2015
12-1662-EL-BNRKIRBY-TANGY 138 KV TRANSMISSION LINE TAP TO CONSOLIDATED ELECTRICS SOUTH SCIOTO SUBSTATION05/23/201203/20/2015
12-2167-EL-BNRPOSTON-ROSS 138 kV REBUILD/RECONDUCTOR PROJECT SECTION 407/26/201207/17/2015
12-2223-EL-BNRBAYSHORE-DECANT 138 KV TRANSMISSION LINE RELOCATION FOR THE OREGON DITCH PROJECT08/03/201203/20/2015
12-2380-EL-BNRGALION-ROBERTS 138 KV TRANSMISSION LINE TAP TO THE US YACHIYO SUBSTATION 08/27/201206/15/2015
12-2446-EL-BNRPOSTON-ROSS 138 kV LINE RECONDUCTOR/REBUILD PROJECT SECTION V09/05/201207/17/2015
12-2480-EL-BNRPOSTON-ROSS 138 kV LINE RECONDUCTOR/REBUILD PROJECT SECTION 609/10/201207/17/2015
12-2524-EL-BNRBLACK RIVER-REPUBLIC ARC 138 KV TRANSMISSION LINE EXTENSION PROJECT09/14/201203/20/2015
12-3003-EL-BNRDP&L BURDOX WEBSTER 138 kV RECONDUCTOR PROJECT11/16/201208/09/2019
12-3004-EL-BNRDP&L SHELBY SUBSTATION UPGRADE11/16/201208/09/2019
12-3005-EL-BNRDP&L GREENE ALPHA 138 kV RECONDUCTOR PROJECT11/16/201208/09/2019
12-3227-EL-BNRCANTON CENTRAL STATION EXPANSION12/17/201208/28/2015
13-1569-EL-BNRDP&L SUGARCREEK/CENTERVILLE 138KV POLE RELOCATION07/02/201308/09/2019
13-1667-EL-BNRDP&L UNDERGROUND OHH SUGARCREEK 138KV RECONDUCTOR07/23/201308/09/2019
13-1843-EL-BNRDUKE ENERGY OHIO FAIRFIELD F-3886 LINE08/26/201308/09/2019
13-2200-EL-BNRHyatt - Corridor 345kV Line 11/12/201308/09/2019
14-0054-EL-BNRHoward - (Melmore)- Fostoria 138kV Line Bypass01/14/201408/09/2019
14-0145-EL-BNRNew Market (SCP) Tap Project01/30/201408/09/2019
14-0241-EL-BNRAEP OHIO / Hillsboro Station Expansion Project02/10/201412/04/2017
14-0529-EL-BNRAEP OHIO TRANSMISSION CO / Sporn - Muskingum River Transmission Line: Muskingum - Waterford 345kV Circuit and Waterford 345kV Ex04/03/201408/09/2019
14-1178-EL-BNRDuke Energy Ohio, Inc./Summerside 138kv Extension07/22/201408/09/2019
14-1577-EL-BNRDP&L Shelby-Sidney 138kV Line Upgrade09/09/201408/09/2019
14-2036-EL-BNRCorner-Parkersburg 138 kV Transmission Line Reconductor Project12/02/201408/09/2019
14-2107-EL-BNRJug Street-Smith's Mill 138kV Transmission Line Project12/09/201408/09/2019
15-0098-EL-BNRPortsmouth Area Structure Relocation Project01/26/201508/09/2019
15-1257-EL-BNRDuke Energy Ohio Fields Ertel Relocation07/08/201509/17/2015
15-1364-EL-BNRFirebrick 138kV Transmission Line Extensions08/28/201508/09/2019
16-0549-EL-BNRBeatty Road Station Drainage Improvements03/11/201612/02/2019
16-1120-EL-BNRRaider 138kV Extension06/16/201608/09/2019
16-1703-EL-BNRHanna-Shalersville 138kV Transmission Line Structure # 12191 Replacement08/18/201607/18/2019
16-1704-EL-BNRHanna-Shalersville 138kV Transmission Line Structure # 12229 Replacement08/18/201607/18/2019
16-1731-EL-BNRClouse Station 138kV Extensions11/17/201612/02/2019
16-2315-EL-BNRGlencoe Station Expansion Part II12/16/201612/01/2017
17-0348-EL-BNREber-Swanton 138 kV Transmission Line Relocation For Norfolk Southern Railway Project02/10/201707/18/2019
17-1241-EL-BNRJackman-GM Powertrain 138kV Transmission Line Project05/12/201709/03/2019
17-1315-EL-BNRMiddleboro Switch Extension05/24/201710/21/2019
17-1416-EL-BNRCanton Central-Cloverdale 138kV-Cloverdale-Torrey 138kV Structure Replacement Project06/09/201708/07/2019
17-1571-EL-BNRInland-Harding (S-8) 345 kV Transmission Line Structure Addition Project07/13/201712/07/2017
17-1673-EL-BNRALLEN JUNCTION-WESTGATE 138 KV TRANSMISSION LINE SWTCH REPLACMENT PROJECT07/26/201708/07/2019
17-2010-EL-BNREast Springfield-Tangy 138 kV Transmission Line Structure Replacement Project09/21/201709/03/2019
17-2190-EL-BNRGalion-Longview 138kV Transmission Line Structure Addition Project10/24/201708/07/2019
17-2444-EL-BNRChamberlin-Hudson 138kV T-Line Structure Replacement Project12/05/201712/06/2019
19-0149-EL-BNRMayfield-Eastlake Q-3 & Q-4 138 kV Transmission Line Tap to Nathan Substation Project01/23/201901/28/2020
19-0445-EL-BNRIn the Matter of the Application of Duke Energy Ohio, Inc., for a Construction Notice for the Wards Corner Project03/01/201906/20/2019
20-1339-EL-BNREber-Swanton 138 kV Second Tap to Johnson Controls Substation Project08/06/202006/22/2021
21-0589-EL-BNRViking 138kV Switch Project06/10/202102/03/2023