06/13/2000 ICN #0006 Letter stating that construction for this project was completed on May 30, 2000, filed on behalf of applicant by G. Cunningham. (1 pg.)
02/16/2000 ICN #0005 Letter stating that construction for this project is scheduled to start on February 14, 2000, filed on behalf of applicant by G. Cunningham. (1 pg.)
12/15/1999 ICN #0004 Letter to Mr. Thomas C. Burgess in response to his Letter of Notification, filed by K. Wissman, PUCO staff. (1 pg.)
12/14/1999 ICN #0003 Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. (1 pg.)
11/15/1999 ICN #0002 Letter regarding the filing of the Letter of Notification, filed on behalf of applicant by T. Burgess. (1 pg.)
11/05/1999 ICN #0001 In the matter of the Letter of Notification of FirstEnergy Corporation on behalf of Toledo Edison Com- pany for the Maclean-Midway 138 kV Tap to Lime City Sub- station. (20 pgs.)