DIS - Case Record for 98-0282-GA-BTX Skip to main content
      
      
CASE NUMBER: 98-0282-GA-BTX
CASE DESCRIPTION: AK STEEL
DOCUMENT SIGNED ON: 4/30/2024
DATE OF SERVICE: ________________________________________
02/28/2002 Memo closing this case of record as of February 28, 2002.
02/07/2002 Construction drawings of AK Steel Corp. filed. (Oversized documents)
06/03/1999 ICN #0040 Certificate of insurance filed on behalf of appli- cant. (1 pg.)
12/24/1998 ICN #0039 Entry ordering that the application of Matrix to transfer its certificate is granted upon the terms set forth in Finding 4. (AE) (2 pgs.)
12/21/1998 ICN #0038 Letter notifying the Commission that construction on the AK Steel pipeline will be completed on December 21, 1998 and the facility will begin commercial operation on January 1, 1999, filed on behalf of applicant by D. Boehm. (1 pg.)
12/18/1998 ICN #0037 Application to transfer certificate of Matrix Gas Corp., filed by D. Boehm. (5 pgs.)
11/04/1998 ICN #0036 Interoffice memorandum to K. Wissman from L. Winget regarding the site visit to the Matrix Pipeline for AKSteel. (1 pg.)
09/17/1998 ICN #0035 Letter to Mr. Donald R. Perander, AK Steel, stating that he may proceed with construction of the portion of the project as depicted on the drawings, filed on behalf of the PUCO staff by K. Wissman. (1 pg.)
09/16/1998 ICN #0034 Engineering drawings filed on behalf of applicant by D. Perander. (1 pg.)
09/14/1998 ICN #0033 Ohio EPA Storm Water General Permit No. OHR10670; U.S. Army Corps of Engiineers Nationwide Permit No. 12; Ohio DOT Permit Nos. 08-0973-97, 08-0974-97, 08-0975-97, 08- 0998-97; Warren County R/W Permit Nos. 97-0838, 97-0839, and 97-0840; and Warren County approval letter dated August 31, 1998, filed on behalf of applicant by D. Perander. (57 pgs.)
09/08/1998 ICN #0032 Letter informing the Commission that construction on the AK Steel pipeline certified in this case will begin on or after September 9, 1998, filed on behalf of applicant by D. Boehm. (1 pg.)
09/01/1998 ICN #0031 Construction Control Plan filed on behalf of applicant by D. Perander. (27 pgs.)
09/01/1998 ICN #0029 Letter to Mr. Donald R. Perander, AK Steel, filed by K. Wissman, PUCO staff. (1 pg.)
09/01/1998 ICN #0030 Letter to Dr. Leon Winget, PUCO staff, regarding construction drawings for this project, filed on behalf of applicant by D. Perander. (2 pgs.)
08/31/1998 ICN #0027 Steam Access Description filed on behalf of applicant by D. Perander. (7 pgs.)
08/31/1998 ICN #0028 Opinion, Order, and Certificate approving the stipulation in its entirety; that a certificate of environ- mental compatibility and public need for this project is hereby issued for the construction, operation, and mainten- ance of such facility; that the certificate shall contain the conditions set forth in Section III of this Order. (19 pgs.)
08/28/1998 ICN #0026 Stormwater Pollution Prevention Plan filed on behalf of applicant by D. Perander. (90 pgs.)
08/27/1998 ICN #0025 Transcript filed for hearing held 8/3/98, (SF), 5 pgs. (Middletown, Ohio)
08/25/1998 ICN #0024 Proof of Publication filed on behalf of applicant by D. Boehm. (3 pgs.) (Butler County)
08/18/1998 ICN #0023 Joint stipulation and recommendation filed on behalf of the PUCO staff by W. Wright and M. Malone; and applicant by D. Boehm. (8 pgs.)
08/18/1998 ICN #0022 Transcript filed for hearing held 8/4/98, (SF), 6 pgs., Continued. (PUCO-Columbus, OH)
08/04/1998 ICN #0019 Response letter to Russel L. Flinchum filed by K. Wissman, PUCO staff. (1 pg.)
08/04/1998 ICN #0021 Response letter to Russel L. Flinchum filed by K. Wissman, PUCO staff. (1 pg.)
08/04/1998 ICN #0020 Comments filed on behalf of R. Flinchum. (3 pgs.)
07/31/1998 ICN #0018 Proof of Publication filed on behalf of appli- cant by D. Boehm. (5 pgs.) (Warren County)
07/17/1998 ICN #0017 Staff Report filed. (35 pgs.)
07/16/1998 ICN #0016 Proof of Publication filed on behalf of applicant by D. Boehm. (4 pgs.) (Butler and Warren Counties)
07/15/1998 ICN #0015 Letter confirming that in response to the OPSB's request, they will modify their plan for boring under I-75 and will now extend the length of the directional boring in order to avoid wetland and preserve trees, filed on behalf of applicant by D. Boehm. (1 pg.)
07/01/1998 ICN #0014 Responses of Matrix Gas Corporation to interro- gatories and request for production of documents, filed by D. Boehm. (5 pgs.)
06/29/1998 ICN #0013 Proofs of Publication filed on behalf of appli- cant by D. Boehm. (5 pgs.) (Warren, Butler Counties)
06/25/1998 ICN #0012 Affidavit and two proofs of publication filed on behalf of Matrix Gas Corp. by D. Boehm. (4 pgs.)
06/23/1998 ICN #0011 Letter informing the Commission that they have identified two "lay down" areas to be used by contractors to temporarily store equipment and materials during con- struction of the pipeline, filed on behalf of applicant by D. Boehm. (1 pg.)
06/16/1998 ICN #0010 Responses of Matrix Gas Corporation to inter- rogatories and request for production of documents filed by D. Boehm. (11 pgs.)
06/04/1998 ICN #0009 Entry scheduling a local public hearing at 7:00 p.m. on August 3, 1998, in Middletown, Ohio; scheduling an adjudicatory hearing at 10:00 a.m. on August 4, 1998, at the Commission offices. (AE) (3 pgs.)
05/27/1998 ICN #0008 Proof of service filed on behalf of Matrix Gas Corp. by D. Boehm. (9 pgs.)
05/18/1998 ICN #0007 Interrogatories and requests for production of documents filed on behalf of the PUCO staff by W. Wright. (12 pgs.)
05/07/1998 ICN #0006 Response letter to Mr. Victory T. Linck filed on behalf of the PUCO staff. (2 pgs.)
04/28/1998 Natural Gas Pipeline and Metering Stations AK Steel Corporation construction specifications. (PART 1 OF 3)
04/23/1998 Natural Gas Pipeline and Metering Stations AK Steel Corporation construction specifications. (PART 2 OF 3)
04/23/1998 ICN# 0005 Standard certificate application filed on behalf of applicant by V. Linck. (477 pgs.)
04/23/1998 Construction specifications-Review. (part 3 of 3)
03/13/1998 ICN #0004 Entry ordering that AK Steel's request for waiver of the time requirement for filing an application is grant- ed. (AE) (1 pg.)
02/27/1998 ICN #0003 Entry ordering that AK Steel's request for waiver of the requirement of filing fully developed information on an alternate route is granted as set forth in Finding 3. (AE) (2 pgs.) (ISSUED 2/25/98)
02/19/1998 ICN #0002 Motion for waiver of requirement of fully develop- ment information on the alternative site designated as alternative and for waiver of time under ORC #4906.06 filed on behalf of applicant by D. Boehm. (7 pgs.)
02/17/1998 ICN #0001 In the matter of the application of the AK Steel Gas Transmission Line Project. (1 pgs.)