10/05/2001
|
Memo closing this case of record. |
06/10/1997
|
ICN #0005 Letter stating that contruction for this project was completed on June 3, 1997, filed on behalf of applicant by G. Cunningham. (1 pg.) |
04/21/1997
|
ICN #0004 Letter stating that construction for the project is scheduled to start on April 4, 1997, filed on behalf of applicant by G. Cunningham. (1 pg.) |
04/04/1997
|
ICN #0003 Letter to C.A. Roteck, Ohio Edison Company, in response to Letter of Notification, filed by K. Wissman, PUCO staff. (1 pg.) (FILED 4/1/97) |
03/31/1997
|
ICN #0002 Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. (1 pg.) |
03/13/1997
|
ICN #0002 In the matter of the Letter of Notification of Ohio Edison Company for Beaver-New Departure 138 KV tap to Brush Engineered Bronze Substation. (30 pgs.) |
|