01/19/2001
|
Memo closing this case of record. |
01/09/1996
|
ICN #005 Letter stating that the construction for this project was completed on December 26, 1995, filed on behalf of Ohio Edison by G. Cunningham. |
08/16/1995
|
ICN #0004 Letter stating that the construction for the Star-West Medina 138 kV Loop to Seville Substation Project is scheduled to commence on August 11, 1995, filed on behalf of applicant by T. Burgess. (1 pg.) |
12/10/1993
|
ICN #0003 Letter in response to Letter of Notification, filed on behalf of the OPSB staff by K. Wissman. |
12/09/1993
|
ICN #0002 Investigation report approving letter of notifi- cation, filed by R. Yerian, M. Pulsinelli, R. Apanius, and J. O'Dell, PUCO staff. |
10/27/1993
|
ICN#0001 Application of the Ohio Edison Company for a letter of notification for the construction of 1.0 miles of new double circuit 138kV transmission line from the Star-West Medina 138kV transmission line to the new Seville Substation. |