04/11/1994
|
ICN #0005 Letter stating that construction was completed on December 10, 1993, filed on behalf of applicant by G. Cunningham. |
11/12/1993
|
ICN #0004 Letter stating that the construction of the project is scheduled to begin on November 11, 1993, filed on behalf of applicant by T. Burgess. |
10/28/1993
|
ICN #0003 Response to Letter of Notification filed on behalf of the OPSB staff by K. Wissman. |
10/27/1993
|
ICN #0002 Site investigation report approving the application filed by J. O'Dell and R. Yerian. |
10/18/1993
|
ICN #0001 In the matter of the Letter of Notifiction of Ohio Edison Company involving the relocation of a 0.21 mile section of the Boardman-Shenango 138 kV transmission line. |