CASE NUMBER: 92-1232-EL-BTX
CASE DESCRIPTION: DAYTON POWER & LIGHT/BLUEJACKET
DOCUMENT SIGNED ON: 4/23/2024
DATE OF SERVICE: ________________________________________
10/16/2000 ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates.
10/16/2000 ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates
10/16/2000 ICN #0044 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. (6 pgs.)
08/21/1996 ICN #0043 Correction to Notice of Termination filed on be- half of applicant by T. Burgess. (PREVIOUSLY FILED ON 7/2/96 INCORRECTLY IN CASE NO. 92-1945-EL-BTX.) (3 pgs.)
08/19/1996 ICN #0042 Correction to the June 24, 1996 filing, submitted on behalf of applicant by T. Burgess. (1 pg.)
05/14/1996 ICN #0041 Letter advising the Commission that the subject project has been completed and was energized on May 8, 1996, filed on behalf of applicant by H. Shamash. (1 pg.)
09/18/1995 ICN #0040 Correspondence letter to Mr. Hertzel Shamash, DP&L, filed by K. Wissman, OPSB staff. (1 pg.)
09/15/1995 ICN #0039 Revised engineering drawings filed on behalf of applicant by H. Shamash. (2 pgs.)
09/06/1995 ICN #0038 Copy of previously provided permits with the new expiration dates, filed on behalf of applicant by T. Bur- gess. (4 pgs.)
08/16/1995 ICN #0037 Correspondence letter to Mr. Hertzel Shamash, DP&L, stating that they may proceed with construction of the project depicted by the drawings, filed by K. Wissman, OPSB staff. (1 pg.)
08/16/1995 ICN #0036 Engineering drawings for work to be completed at Blue Jacket Substation, filed on behalf of applicant by H. Shamash. (1 pg.)
05/31/1995 ICN #0035 Final certificate of plan approval for con- struction of the Kirby Substation Control Building from the Ohio Department of Industrial Relations, filed on behalf of applicant by T. Burgess. (3 pgs.)
05/23/1995 ICN #0034 ODOT permits for crossing State Route 292 and U.S. Route 68 filed on behalf of applicant by H. Shamash. (12 pgs.)
05/01/1995 ICN #0033 State of Ohio Department of Transportation permits to cross state routes 31 and 739 in Union County, Ohio filed on behalf of DP&L by H. Shamash. (5 pgs.)
04/18/1995 ICN #0032 Letter to Mr. Hertzel Shamash, DP&L, stating that the company may proceed with construction of the portion of the project depicted by the engineering drawings, filed by K. Wissman, OPSB staff. (1 pg.)
04/14/1995 ICN# 0031 Revised engineering drawings entitled Plan & Profile drawing T2-372-F, Sheet 2, Revision A filed on behalf of DP&L by H. Shamash (2 pgs)
04/13/1995 ICN #0030 Erosion control plan for the Locan County portion of this project, filed on behalf of applicant by S. Shamash. (3 pgs.)
03/16/1995 ICN #0029 Union County concurrence letter including the Company's February 23, 1995 review materials, filed on behalf of applicant by T. Burgess. (3 pgs.)
03/10/1995 ICN #0028 Letter of concurrence from the Ohio Historic Preservation Office regarding the scope and conclusions of the Phase I Archaeological Studies performed on the certified route, filed on behalf of applicant by H. Sham- ash. (4 pgs.)
02/24/1995 ICN #0027 Required highway crossing permits for two locations of S.R. 37 for the Ohio Edison portion of the Bluejacket-Kirby 138 kV transmission line project, filed by T. Burgess. (6 pgs.)
02/13/1995 ICN #0025 Engineering drawings filed on behalf of DP&L by H. Shamash. (50 pgs.)
02/13/1995 ICN #0026 Letter stating that the engineering/construction drawings have been reviewed by the staff, and that the company may proceed with the construction of the project, filed on behalf of the OPSB staff by K. Wissman. (1 pg.)
09/20/1993 ICN #0024 Order approving the joint stipulation regarding the application to amend the certificate.
07/30/1993 ICN #0023 Transcript filed for hearing held 7/15/93, (SD), 8 pgs., Submitted.
07/23/1993 ICN #0022 Transcript filed for hearing held 7/14/93, (SD), 5 pgs., Con't. (Bellefontaine, Ohio)
06/28/1993 ICN #0021 Staff report filed.
05/27/1993 ICN #0020 Proof of publication filed on behalf of applicant by E. Rizer. (Union County)
05/05/1993 ICN #0019 Entry scheduling a local public hearing at 7:00 p.m. on 7/14/93 at the City Building, Belle- fontaine, Ohio; the adjudicatory hearing will commence at 10:00 a.m. on 7/15/93 at the Commission offices. (OPSB)
04/22/1993 ICN #0018 Certificate of service filed on behalf of applicant by E. Rizer.
04/07/1993 ICN #0017 Letter to A. M. Hill stating that the application to amend the Richwood-Blue Jacket 138 kV project has today been certified as being complete, filed by C. Glazer, PUCO staff.
02/18/1993 ICN #0016 Application for amendment to a certificate of environmental compatibility and public need, filed on behalf of applicant by A. Hill.
01/25/1993 ICN #0014 Correspondence letter objecting to application, filed by S. Hopper.
01/25/1993 ICN #0015 Opinion & Order approving the stipulation and recommendation in its entirety. (OPSB)
01/20/1993 ICN #0013 Transcript filed for hearing held 1/7/93, (SD), 12 pgs., Submitted.
01/08/1993 ICN# 0012 Transcript for public hearing held January 6, 1993, (SD) 36 pages, Continued.
01/07/1993 ICN #0011 Joint Exhibit No. 2, joint stipulation and recom- mendation filed on behalf of DP&L by E. Rizer; Ohio Edison by M. Beiting; and the OPSB staff by L. Angell.
01/07/1993 ICN #0010 Reffit Exhibit 1 filed.
12/22/1992 ICN #0009 Staff Report filed.
12/21/1992 ICN #0008 Proof of publication filed on behalf of applicant by E. Rizer. (Union and Logan Counties)
12/09/1992 ICN #0007 Response to the staff of the Ohio Power Siting Board's first request for production of documents and first set of interrogatories, filed on behalf of Ohio Edison by M. Beiting.
11/12/1992 ICN #0006 Notice of appearance filed on behalf of the OPSB staff by L. Angell.
10/13/1992 ICN #0005 Notice of appearance filed on behalf of Ohio Edison by M. Beiting.
10/09/1992 ICN #0004 Entry scheduling public hearing at 7:00 p.m. on 1/6/93 at the City Building, Bellefontaine, Ohio; the adjudicatory hearing at 10:00 a.m. on 1/7/93 at the Commission offices. (OPSB)
09/25/1992 ICN #0003 Proof of service of the application filed on behalf of applicant by E. Rizer.
09/03/1992 ICN #0002 Letter to Thomas M. Jenkins stating that this project has today been certified as being complete, filed on behalf of the OPSB staff by Chairman Glazer.
07/10/1992 ICN #0001 In the matter of the application of The Dayton Power & Light Company for certificate of environmental compatibility and public need, Richwood - - Blue Jacket 138 kV Transmission Line.