CASE NUMBER: 91-2020-EL-BLN
CASE DESCRIPTION: OHIO EDISON COMPANY
DOCUMENT SIGNED ON: 11/29/2020
DATE OF SERVICE: ________________________________________
10/08/1993 Memo closing case with effective date of 10/8/93.
05/28/1992 ICN #0005 Letter stating that the construction was completed on May 15, 1992, filed on behalf of applicant by T. Burgess.
05/12/1992 ICN #0004 Letter stating that construction of this project is to begin on April 6, 1992, filed on behalf of applicant by T. Burgess.
11/26/1991 ICN #0003 Letter in response to Letter of Notification filed on behalf of the OPSB staff by J. Kennedy.
11/26/1991 ICN #0002 Investigation Report Letter of Notification filed on behalf of the OPSB staff.
11/05/1991 ICN #0001 Letter of Notification describing the replacement of four wood pole structures on the centerline of the existing Johnson-U. S. Steel 138 kV transmission line.