CASE NUMBER: 91-1421-EL-CSS
CASE DESCRIPTION: M COGSWELL/TOLEDO ED/NORTHWESTERN E
DOCUMENT SIGNED ON: 4/19/2024
DATE OF SERVICE: ________________________________________
08/10/1994 Semiannual report filed on behalf of respondent, Toledo Edison, by M. Regulinski.
01/14/1994 Semi-annual report filed on behalf of respondent, Toledo Edison, by M. Regulinski.
07/22/1993 Supplemental opinion and order be denied, that the complaint be dismissed, and that this case be closed of record; that Toledo Edison Company file with the Compliance Division of this Commission's Consumer Services Department, semi-annual reports for the next year reflecting the quality of service provided the complainants including outages, interruption of service, and any re- medial actions taken
07/22/1993 Supplemental Opinion & Order that the complainants' request to be served by Northwestern Electric Co-Operative be denied, that the complaint be dismissed, and that this case be closed of record; that Toledo Edison Company file with the Compliance Division of this Commission's Consumer Services Department, semi-annual reports for the next year reflecting the quality of service provided the complaiants including outages, interruption of service, and any re- medial actions taken.
06/09/1993 Transcript filed for hearing held 5/18/93, (SF), 16 pgs., Submitted.
05/10/1993 Written testimony of Richard J. McDanel filed on behalf of respondent, Toledo Edison Company, by M. Regulinski.
04/13/1993 Entry ordering that the hearing in this proceeding be reopened for the purpose of taking additional testimony regarding the staff report filed in this case; scheduling the hearing at 1:00 p.m. on 5/18/93 at the Commission offices. (AE)
04/05/1993 Additional information filed on behalf of complainant by M. Cogswell.
03/25/1993 Entry denying Toledo Edison's application for rehearing.
03/15/1993 Staff report filed on behalf of the PUCO staff.
03/08/1993 Application for rehearing filed on behalf of Toledo Edison Company by M. Regulinski.
02/04/1993 Opinion & Order that the staff undertake an investigation into the matter to confirm that the respondent has taken all necessary steps to insure that respondent has furnished adequate facilities to meet the reasonable needs of the complainant; that the staff report shall be filed with the Commission by 3/15/93; that either party may reopen the hearing within 20 days of the filing of staff report.
11/16/1992 Correspondence letter stating that complainant will not drop complaint, filed by M. Cogswell.
11/02/1992 Motion to dismiss and memorandum in support filed on behalf of respondent, Toledo Edison, by M. Regulinski.
11/02/1992 Brief filed on behalf of respondent, Toledo Edison, by M. Regulinski.
10/21/1992 Transcript filed for hearing held 9/30/92, (SF), 151 pgs., Submitted. (Montpelier, Ohio)
09/22/1992 Written testimony of Michael J. Titas filed on behalf of Toledo Edison by M. Regulinski.
09/22/1992 Written testimony of Clarence Hartzell, III filed on behalf of Toledo Edison by M. Regulinski.
08/07/1992 Entry rescheduling the hearing from 8/28/92 to 9/30/92 at 10:30 a.m., Montpelier, Ohio. (AE)
07/23/1992 Entry scheduling hearing at 10:00 a.m. on 8/28/92 at the Commission offices. (AE)
07/21/1992 Letter requesting a hearing in this complaint, filed on behalf of complainants by Mary and Earl Cogswell.
07/21/1992 Letter requesting that a hearing not be scheduled and that the complaint be dismissed, filed on behalf of respondent, Toledo Edison, by M. Regulinski.
07/07/1992 Entry ordering that the complainants notify the Commission in writing by 7/24/92 whether they wish to proceed with a hearing. (AE)
12/18/1991 Entry ordering that the six month stay commencing December 17, 1991 and continuing until June 17, 1992 is granted, during which time both the respondent and the complainants shall evaluate improvements made to the complainant's electrical service; that upon the expiration of the six-month time period compalainants shall re-evaluate their complaint and inform the Commission, by 6/30/92, of whether they wish to proceed to a hearing. (AE)
12/13/1991 Correspondence letter filed by M. Cogswell.
11/26/1991 Entry ordering that the 12/5/91 hearing shall be converted to a prehearing conference. (AE)
11/22/1991 Proof of Publication filed. (Williams County)
11/15/1991 Entry ordering that Mary Cogswell is designated as spokesperson for all complainants in this case; that the respondent's motion for certification of the interlocutory appeal is denied. (AE)
11/13/1991 Letter stating that petitioners want to continue to pursue this complaint, filed on behalf of complainant by M. Cogswell.
11/12/1991 Motion to continue hearing and brief in support filed on behalf of respondent, Toledo Edison Co., by M. Regulinski.
10/28/1991 Legal notice sent to the Bryan Times (Williams County).
10/28/1991 Legal notice sent to the Bryan Times (Williams).
10/22/1991 Motion to accept filing as timely and motion to certify an interlocutory appeal to the Commission, filed on behalf of respondent, Toledo Edison, by M. Regulinski.
10/16/1991 Entry ordering that a hearing be scheduled at 10:00 a.m. on 12/5/91 at the Village Town Hall, Council Chambers, Montpelier, Ohio; that legal notice of public hearing be published as set forth in Finding 5. (AE)
09/30/1991 Motion to dismiss or in the alternative answer, and brief in support of motion to dismiss, filed on behalf of respondent, Toledo Edison, by M. Regulinski.
09/10/1991 Entry granting Toledo Edison Company until 9/30/91 to file an answer or motion. (AE)
09/09/1991 Motion for an extension of time to file an answer or motion to the complaint, filed on behalf of respondent, Toledo Edison, by M. Regulinski.
08/07/1991 Complaint letter and copy of complaint sent to: Toledo Edison Company, office of the president.
08/02/1991 In the matter of the petition of Mary E. Cogswell and various customers of Toledo Edison Company to change their electric service to Northwestern Electric Co-Operative.