11/27/1991
|
Entry dismissing case. |
11/01/1991
|
Protest withdrawn on behalf of PG&E Bechtel Generating Company by W. Newcomb, Jr. |
10/24/1991
|
Joint status report on the status of the negotiations between CG&E and PG&E Bechtel filed by W. Newcomb, Jr. |
10/17/1991
|
Letter regarding the status of Armco Steel in this proceeding, filed on behalf of Armco Steel by D. Boehm. |
10/16/1991
|
Transcript for hearing held September 26, 1991, (SD) 6 pages, Submitted. |
10/10/1991
|
Joint status report on the status of the negotiations between CG&E and PG&E Bechtel, filed by W. Newcomb, Jr. |
09/30/1991
|
Proofs of publication filed. (Hamilton, Clinton, Preble, Warren, Butler, Highland, Brown, Adams, and Clermont Counties) |
09/25/1991
|
Motion for continuance of hearing and memorandum in support, filed on behalf of PG&E Bechtel by W. Newcomb, Jr. |
09/25/1991
|
Memorandum contra filed on behalf of CG&E by M. Gribler. |
09/20/1991
|
Rebuttal testimony of Hethie S. Parmesano filed on behalf of CG&E by M. Gribler. |
09/20/1991
|
Rebuttal testimony of Donald I. Marshall filed on behalf of CG&E by M. Gribler. |
09/20/1991
|
Transcript filed for hearing held 9/10/91, (SD), 4 pgs., Con't. |
09/18/1991
|
Motion to strike testimony and request for expedited ruling and memorandum in support filed on behalf of the PUCO staff by D. Luckey. |
09/18/1991
|
Reply memorandum filed on behalf of applicant by W. Newcomb, Jr. |
09/18/1991
|
Motion for leave to file reply memorandum and memorandum in support filed on behalf of applicant by W. Newcomb, Jr. |
09/17/1991
|
Corrections to Staff Findings and Recommendations, filed on behalf of the PUCO staff by D. Luckey. |
09/12/1991
|
Revised Exhibit (HSP-8), Schedule 2 of the direct testimony of Dr. Hethie Parmesano, filed on behalf of CG&E by M. Gribler. |
09/12/1991
|
Memorandum in opposition to the motion to strike testimony and request for expedited ruling of PG&E/Bechtel Generating Company, filed on behalf of Armco Steel Company, L.P. by D. Boehm. |
09/11/1991
|
Entry rescheduling the prehearing conference from 10:00 a.m. on 9/6/91 to 10:00 a.m. on 9/25/91; rescheduling the hearing from 10:00 a.m. on 9/10/91 to 10:00 a.m. on 9/26/91. (AE) |
09/11/1991
|
Memorandum contra filed on behalf of CG&E by M. Gribler. |
08/30/1991
|
Motion to strike testimony and request for expedited ruling filed on behalf of PG&E Bechtel Generating Company by W. Newcomb, Jr. |
08/29/1991
|
PUCO Staff Findings and Recommendations filed by D. Luckey. |
08/28/1991
|
Motion to authorize appearance filed on behalf of CG&E by M. Gribler. |
08/28/1991
|
Direct testimony of Hethie S. Parmesano filed on behalf of CG&E by M. Gribler. |
08/28/1991
|
Direct testimony of Donald I. Marshall filed on behalf of CG&E by M. Gribler. |
08/28/1991
|
Direct testimony and exhibits of Stephen J. Baron, filed on behalf of Armco Steel Company, L.P. by D. Boehm. |
08/28/1991
|
Direct testimony of James G. Utt filed on behalf of PG&E-Bechtel by W. Newcomb, Jr. |
08/28/1991
|
Direct testimony of William B. Marcus filed on behalf of PG&E-Bechtel by W. Newcomb, Jr. |
08/28/1991
|
Direct testimony of Ernest K. Hauser filed on behalf of PG&E-Bechtel by W. Newcomb, Jr. |
07/24/1991
|
Entry granting Armco's motion to intervene. (AE) |
07/18/1991
|
Entry scheduling a prehearing conference at 10:00 a.m. on 9/6/91 and a hearing at 10:00 a.m. on 9/10/91, both at the Commission offices; CG&E should cause legal notice to be published. (AE) |
06/12/1991
|
Counter response to the position statement and justification of PG&E/Bechtel Generating Company, filed on behalf of Armco Steel Company, L.P. by D. Boehm. |
06/11/1991
|
Counter response filed on behalf of The Cincinnati Gas & Electric Company by M. Gribler. |
06/11/1991
|
Counter response to filings of the Cincinnati Gas & Electric Company and Armco Steel Company, L.P., filed on behalf of PG&E-Bechtel Generating Company by W. Newcomb, Jr. |
05/13/1991
|
Position statement and justification filed on behalf of PG&E Bechtel Generating Company by W. Newcomb, Jr. |
05/13/1991
|
Position statement and justification filed on behalf of Armco Steel Company, L.P. by M. Kurtz. |
05/13/1991
|
Position statement filed on behalf of applicant, CG&E, by M. Gribler. |
04/15/1991
|
Motion to intervene filed on behalf of Armco Steel Company, L.P. by M. Kurtz. |
03/28/1991
|
Entry ordering this docket be opened for the purposes of deciding the issues concerning avoided cost rates, and terms and conditions for cogenerated power trans- actions between CG&E and Bechtel and adopting the Staff's recommended procedures set forth in Attachment 1 and 2 to this entry. |
02/21/1991
|
In the matter of the Commission determination of appropriate cogeneration rates for power transactions between Cincinnati Gas & Electric and PG&E Bechtel. |