CASE NUMBER: 91-0278-EL-BLN
CASE DESCRIPTION: TOLEDO EDISON COMPANY
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
10/08/1993 Memo closing case with effective date of 10/8/93.
03/12/1991 ICN #0004 Letter stating that the planned date of initial construction on this project is the week of March 4, 1991, filed on behalf of applicant by J. Ams, Sr.
02/28/1991 ICN #0003 Investigation report for Letter of Notification filed on behalf of OPSB staff.
02/28/1991 ICN #0002 Letter to Craig I. Smith, senior corporate counsel Centerior Energy, in response to Letter of Notification filed February 11, 1991, filed on behalf of the OPSB by J. Kennedy.
02/11/1991 ICN #0001 Letter of notification covering the installation of a single circuit l38kV supply line to the Manville Customer Distribution Substation, filed by The Toledo Edison Company.