CASE NUMBER: 89-1604-RR-CSS
CASE DESCRIPTION: CO-OP LEGS COMM VS CONRAIL
DOCUMENT SIGNED ON: 5/2/2024
DATE OF SERVICE: ________________________________________
08/02/1990 Entry dismissing case.
07/18/1990 Letter to R. Patterson, PUCO staff, stating that the vans presently in service to transport Conrail crews have been equipped in accordance with the letter of understanding, filed on behalf of complainant by R. Deal.
07/06/1990 Inspection report filed on behalf of the staff of the PUCO by R. Patterson.
02/26/1990 Agreement reached by the parties in case filed on behalf of respondent by R. Stroh.
02/13/1990 Entry ordering that Co-op should inform the Commission by 6/1/90 whether or not the work called for under the agreement has been completed and if this case whould be dismissed or scheduled for hearing. (AE)
02/05/1990 Transcript filed for hearing held 1/31/90, (MF), 8 pgs., Submitted, Vol. I.
02/01/1990 Letter sent to Mark Adams from W. Wright, PUCO Staff, stating that decision in this case be deferred pending completion of installation of the "fish net" safety restraints in all vans which Milepost, Inc. uses to serve Conrail needs.
01/11/1990 Entry continuing hearing to 1/31/90 at l0:00 A.M. at the PUCO. (AE)
01/09/1990 Letter requesting hearing be continued to 1/31/90 filed on behalf of PUCO Staff by W. Wright.
12/01/1989 Entry scheduling hearing for January 16, 1990 at 10:00 a.m. at the office of the Commission. (AE)
11/22/1989 Answer filed on behalf of respondent by R. Stroh.
11/17/1989 Letter filed on behalf of Conrail requesting an extension of time to file their answer filed by R. Stroh.
11/02/1989 Complaint letter sent to the respondent.
10/30/1989 In the matter of the complaint of Co-Operative Legislative Committee for alleged unsafe conditions of Conrail, Buckeye Yard, Columbus, Ohio.