04/07/2003 Additional information on behalf of applicant filed by T. Krauss.
11/08/2000 ICN #0071 Westland delineation December 2000 report filed on behalf of applicant by T. Krauss. (82 pgs.)
10/16/2000 ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates.
10/16/2000 ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates
10/16/2000 ICN #0070 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. (6 pgs.)
11/04/1999 ICN #0069 December 1999 report filed on behalf of applicant by G. Cunningham. (110 pgs.)
11/04/1999 ICN #0069 December 1999 report filed on behalf of applicant by G. Cunningham. (110 pgs.)
01/14/1999 December 1998 wetlands mitigation report filed by G. Cunningham on behalf of Ohio Edison.
05/29/1996 ICN #0067 Letter advising the Commission that during the previous six months operation (November 1, 1995-April 30 1996), there were no citizen complaints or equipment problems associated with the project, filed on behalf of applicant by T. Burgess. (1 pg.)
12/04/1995 ICN #0066 Semi-annual report of citizen complaints and equipment problems, filed on behalf of applicant by T. Burgess. (1 pg.)
05/31/1995 ICN #0064 Semi-annual report of citizen complaints and equipment problems filed on behalf of applicant by T. Burgess. (1 pg.)
12/19/1994 ICN #0063 Semi-annual report filed on behalf of applicant by T. Burgess. (1 pg.)
11/16/1994 ICN #0062 Ohio EPA response dated 6/20/94 filed on behalf of applicant by T. Burgess. (2 pgs.)
05/24/1994 ICN #0061 Letter stating that the construction was com- pleted on May 17, 1994, filed on behalf of applicant by T. Burgess.
01/12/1994 ICN #0060 Letter stating that Ohio Edison plans to begin construction of the 345 kV transmission line portion of the Chamberlin 345-138 kV project on January 17, 1994, filed by T. Burgess.
04/29/1993 ICN #0059 Letter to T. C. Burgess stating that applicant may proceed with construction of the portion of the project depicted on the drawings submitted on April 19, 1993, filed by K. Wissman, OPSB staff.
04/21/1993 ICN #0058 Detailed engineering construction drawings as, listed on Exhibit 1, which Ohio Edison plans to initiate on May 1, 1993, filed by T. Burgess.
04/21/1993 ICN #0057 Revised SWMP Plan approved by Summit County, and recent notification letter to OEPA, filed on behalf of applicant by T. Burgess.
09/10/1992 ICN #0056 Letter stating that the construction for the Chamberlin 345-138 kV project began on August 3, 1992, filed on behalf of applicant by T. Burgess.
07/02/1992 ICN #0055 Compliance notification filed on behalf of applicant by T. Burgess.
05/12/1992 ICN #0054 Section 404 Permit in satisfaction of the Certificate condition, filed on behalf of applicant by T. Burgess.
02/06/1992 Service Notice
02/05/1992 ICN No. 0053, Opinion and Order, ordering that the Joint stipulation of findings and recommendations submitted in this proceeding is hereby approved in its entirety, that the certificate of Environmental Compatibility and Public Need for the Chamberlin 345-138kV project is hereby issued .
02/05/1992 ICN #0053 Opinion & Order approving joint stipulation and recommendation; that the certificate of environmental compatibility and public need for the Chamberlin 345-138kV project is hereby issued to allow the construction, operation, and maintenance of such facility; that certifi- cate shall contain the conditions set forth in Section III of the Opinion. (OPSB)
01/21/1992 ICN No. 0052, Transcript of proceedings before Administrative Law Judge Denise Clayton on January 10, 1992. (submitted)
01/21/1992 ICN #0052 Transcript filed for hearing held 1/10/92, (DC), 11 pgs., Submitted.
01/10/1992 ICN #0051 Joint stipulation of findings and recommendations filed on behalf of applicant by M. Beiting; OPSB staff by S. Farolino; City of Macedonia by J. Diemert, Jr.
11/08/1991 ICN No. 0050, Testimony of Thomas C. Burgess, Warren C. High, Garry R. Engmann and Garrett Hollands, filed on behalf of Ohio Edison Company.
11/08/1991 ICN #0050 Prefiled testimony of the following persons, filed on behalf of applicant by M. Beiting: 1. Thomas C. Burgess 2. Warren C. High 3. Gary R. Engmann 4. Garrett Hollands
10/31/1991 ICN #0049 Transcript filed for hearing held 10/16/91, (DC), 25 pgs., Submitted.
10/30/1991 ICN #0048 Supplemental responses to Staff requests 2.4, 2,7 and 2.35 filed on behalf of applicant by M. Beiting.
10/25/1991 ICN #0047 Transcript filed for hearing held 10/17/91, (DC), 4 pgs., Submitted.
10/01/1991 ICN #0046 Staff Report filed.
10/01/1991 ICN No. 0046, Staff Report filed.
09/24/1991 ICN #0045 Entry granting Ohio Edison's motion for prehearing conference; scheduling prehearing conference at 1:00 p.m. on 10/7/91 at the Commission offices. (OPSB)
09/16/1991 ICN #0044 Motion for prehearing conference and memorandum in support filed on behalf of applicant by M. Beiting.
09/04/1991 ICN #0043 Notice of intervention filed on behalf of the city of Macedonia by J. Diemert, Jr.
08/30/1991 ICN# 0042 Ohio Edison's responses to second set of interrogatories and requests for production of documents filed by M. Beiting.
08/30/1991 ICN# 0041 Proof of publication filed on behalf of the applicant by M. Beiting.
08/09/1991 ICN #0040 Entry scheduling local public hearing at 7:00 p.m. on 10/16/91 at City Hall, Twinsburg, Ohio, and adjudicatory hearing at 10:00 a.m. on 10/17/91 at the Commission offices; that notice of the hearings be published by Ohio Edison Company. (OPSB)
08/09/1991 ICN #0039 Staff's second set of interrogatories and requests for production of documents propounded to Ohio Edison Company, filed by S. Farolino.
08/05/1991 ICN #0038 Certified amendment to the Board as requested by the Staff, filed on behalf of applicant by B. Miller.
07/18/1991 ICN #0037 Correspondence letter to Mr. Michael R. Beiting, Ohio Edison, regarding the certified amended application for the Chamberlin 345-138 kV Project, filed on behalf of the PUCO staff by Chairman C. Glazer.
06/04/1991 ICN# 0036 Amendment to the short form application filed on behalf of the applicant by M. Beiting.
05/24/1991 ICN #0035 Revised and supplemental responses and objections to staff's first set of interrogatories and requests for production of documents filed on behalf of applicant by M. Beiting.
04/29/1991 ICN #0034 Letter regarding a meeting between the company and the OPSB staff, filed on behalf of applicant by M. Beiting.
04/08/1991 ICN #0033A Response to Michael R. Beiting's letter of January 11, 1991, filed on behalf of the PUCO staff by M. Malone.
02/22/1991 ICN #0033 Letter stating that the public hearing scheduled on February 25, 1991, in Twinsburg, Ohio, has been postponed indefinitely, filed on behalf of applicant by T. Burgess.
02/08/1991 ICN #0032 Entry ordering that issuance of a Staff Report in this matter is held in abeyance; the hearings in this matter scheduled for February 25 and 26, 1991, are stayed until further notice; company is required to post conspicuous notice at the location of the public hearing on February 25, 1991, in order to notify any members of the public of the status of this proceeding. (OPSB)
02/05/1991 ICN #0031 Response to Ohio Edison Company's notice of intent to amend application and motion to hold issuance of staff report and hearings in abeyance, filed on behalf of the OPSB staff by S. Farolino.
02/04/1991 ICN# 0030 Notice of intent to amend certified application motion to hold issuance of staff report and public hearing in abayance filed on behalf of the applicant by M. Beiting.
01/31/1991 ICN #0029 Responses and objections to Staff's first set of interrogatories and requests for production of documents propounded to Ohio Edison, filed on behalf of applicant by M. Beiting.
01/11/1991 ICN #0028 Letter requesting that Mr. Kennedy's (OPSB staff) letter of December 12, 1990 to Linda Merchant (OEPA staff) be disavowed immediately, filed on behalf of applicant by M. Beiting.
01/07/1991 ICN #0027 Letter to the Army Corps of Engineers filed on behalf of applicant by M. Beiting.
01/04/1991 ICN #0026 First set of interrogatories and requests for production of documents propounded to Ohio Edison filed on behalf of OPSB staff by S. Farolino.
12/26/1990 ICN #0025 Entry ordering that Ohio Edison's publication notice of this proceeding is deemed to be in substantial compliance with the Board's rules; all persons will have until January 7, 1991, to file a petition for leave to intervene. (OPSB)
12/14/1990 ICN #0024 Proof of notice filed on behalf of applicant by M. Beiting.
12/14/1990 ICN #0023 Motion for order accepting public notice as in substantial compliance with Section 4906.06(C), Revised Code and Rule 4906-5-07(A) and memorandum in support filed on behalf of applicant by M. Beiting.
12/13/1990 ICN #0022 Letter filed on behalf of the OPSB stating that the respective substation configurations are practicable and the staff has accepted the for consideration of certification by the Board filed by J. Kennedy.
11/21/1990 ICN #0021 Entry scheduling local public hearing on 2/25/91 at 7:00 p.m., City Hall, Twinsburg, Ohio; adjudicatory hearing on 2/26/91 at l0:00 a.m. at the Commission offices; notice of hearings must be published by Ohio Edison. (OPSB)
11/06/1990 ICN #0020 Affidavit of Service filed on behalf of applicant by B. Miller.
10/15/1990 ICN #0019 Letter stating that application for the Chamberlin 345-138 kV Project received February 23, l990, has today been certified, filed on behalf of the OPSB by Chair Butler.
09/07/1990 ICN# 0018 Second addendeum materials filed on behalf of the applicant by M. Beiting.
08/13/1990 ICN #0017 Addendum to application filed on behalf of applicant by M. Beiting.
06/25/1990 ICN# 0016 Correspondent letter sent to M. Beiting filed on behalf of Chair Butler stating that the staff has reviewed the responses of letter dated May 25, 1990 and find that the application deemend incomplete.
05/25/1990 ICN# 0015 Response filed on behalf of the applicant filed by M. Beiting.
05/22/1990 ICN #0014 Notice of appearance filed on behalf of the OPSB by S. Farolino.
05/01/1990 ICN #0013 Technical consideration letter filed on behalf of applicant by C. Fleming.
04/27/1990 ICN #0012 Letter stating why the application was rejected based on requirements listed, filed on behalf of the OPSB by Chair Butler.
04/05/1990 ICN #0011 Addendum Materials to application for Certificate previously transmitted on February 22, l990, filed on behalf of applicant by B. Miller.
04/03/1990 ICN# 0010 Letter sent to Mr. Lichvar of the Buffalo Distric Army Corps of Engineers by J. Kennedy.
03/12/1990 ICN #0009 Amended pages to original application filed on behalf of applicant by W. High.
02/23/1990 ICN #0008 Short Form Application for Certification of the Chamberlin 345-l38 kV Project, Summit County, Ohio, filed by B. Miller.
11/20/1989 ICN# 0007 Correspondent letter filed on behalf of ODNR by J. Rupert.
09/05/1989 ICN. #0006 Entry ordering that Ohio Edison Company's request for a waiver of the one-year filing requirement set forth in Section 4906.06(A) (6), Revised Code; Ordering that Ohio Edison Company's request for waive of the "twenty Percent" requirement set forth in Rule 4906-5-03(A)(2)(a) (iii), O.A.C, is granted with regard to the Chamberlin site, but not to any subsequent transmission lines which may be in- cluded as part of other alternative in this proceeding; Ordering that Ohio Edison Company's request to waive sub- mission of data for an alternative substation site is denied. (AE)
08/23/1989 ICN. #0005 Request to waive the requirement of Rule 4906.-5 -03(A) (2)(a) (iii) O.A.C., filed by M. Beiting on behalf of applicant.
08/23/1989 ICN. #0004 Request to waive submittal of alternate sub- station site data filed by M. Beiting on behalf of applicant
08/23/1989 ICn. #0003 Request to waive one-year filing requirement prior to construction filed by M. Beiting on behalf of applicant.
07/20/1989 ICN. #0002 Withdrawal of Request for Pre-Application Conference filed by T. Burgess on behalf of applicant.