04/17/1996
|
ICN #0024 Notice of start of commercial operation, April 18, 1994, filed on behalf of applicant by K. Hegemann. (2 pgs.) |
05/24/1993
|
ICN# 0024 Entry ordering that the certificate of environmental compatibility and public need is hereby amended to permit construction. (OPSB) |
04/06/1993
|
ICN #0023 Letter stating that applicant has served copies of the certified amendment to public officials and libraries, filed by C. Scheer. |
04/06/1993
|
ICN #0022 Proofs of publication filed on behalf of applicant by C. Scheer. (Marietta Times, Parkersburg News, and Parkersburg Sentinel) |
03/09/1993
|
ICN #0021 Entry granting Amendment to the certificate which was filed 2/12/93 and ordering applicant to serve a copy of the application upon such persons and parties as set forth in Rule 4906-5-09(B)(1), O.A.C.. (OPSB) |
02/12/1993
|
ICN #0020 Amendment No. 1 to the application, filed on behalf of applicant. |
03/20/1991
|
ICN #0019 Letter stating that applicant has met the conditions set forth in Section III of the Opinion and Order, filed by C. Scheer. |
01/16/1991
|
ICN #0018 Letter stating that the starting date of commercial operation is December 14, 1990 and and completion date is December 4, 1990, filed on behalf of applicant by K. Hegemann. |
03/07/1990
|
ICN #00l6 Letter stating thatfacility represented on Drawings l0l0-E800-0l5-00 to l0l0-E800-034-00 and l0l0-CS300-0l0-00 to l0l0-CS300-0l4-00 is consistent with the facility certificated in this case and construction may be proceeded filed by J. Kennedy. |
03/07/1990
|
ICN# 0017 Specifications for substation construction filed on behalf of the applicant by GPD Associates. |
12/20/1989
|
ICN# 0015 Letter filed on behalf of the OPSB stating that the spec's are consistent and the applicant may proceed with the construction filed by J. Kennedy. |
12/14/1989
|
ICN# 0014 Specifications and maps filed on behalf of the applicant by GPD Associates. |
12/11/1989
|
ICN# 0013 Opinion and Order and Certificate issued. |
12/11/1989
|
ICN# 0012 Transcript for public hearing held November 14, 1989, (GR), 5 pages, Continued. |
12/05/1989
|
ICN# 0011 Replacement page 2 for the Joint Stipulation filed on behalf of the OPSB by M. Malone. |
12/04/1989
|
ICN# 0009 Transcript for hearing held November 15, 1989, (RG) 8 pages, Submitted. |
11/17/1989
|
ICN# 0008 Joint stipulation of finding and recommendations filed on behalf of the parties by J. Bentine and M. Malone |
10/31/1989
|
ICN# 0007 Notice of appearance filed on by M. Malone. |
10/26/1989
|
ICN# 0006 Staff report filed |
10/19/1989
|
ICN. #0005 Proofs of Publications filed by K. Hegemann on behalf of applicant. |
08/31/1989
|
ICN. #0004 Entry scheduling hearing to be held on 11/14/89, at 7:00 p.m., at the Washington County Department of Human Services Assembly Room, 223 Putnam, Marietta, Ohio. The adjudicatory hearing will commence on 11/15/89, at 10:00 a.m at the offices of the Commission. (AE) |
08/23/1989
|
ICN. #0003 Letter filed by K. Hegemann on behalf of applicant, with list of names of local government officals that that have been served the application. |
07/17/1989
|
ICN. #0002 Letter filed by Chair Butler, to C. Scheer, RE: filing of information. |
05/26/1989
|
ICN. #0001 Application for certification of the Gorsuch Power Plant 138 kV Substation Project Washington County, Ohio by American Municipal Power-Ohio, Inc. |