DIS - Case Record for 88-0017-GA-GCR Skip to main content
      
      
CASE NUMBER: 88-0017-GA-GCR
CASE DESCRIPTION: EASTERN NATURAL GAS COMPANY
DOCUMENT SIGNED ON: 5/6/2024
DATE OF SERVICE: ________________________________________
11/22/1988 Opinion & Order approving the joint Stipulation and Recommendation and closing case.
11/15/1988 Entry ordering that the motions of Eastern and the Staff to strike OCC Exhibit 1, or portions thereof, be denied: Ordering OCC Exhibit 1 be admitted into evidence. (AE)
10/07/1988 Post-Hearing Brief of The Office of the Consumers' Counsel and memorandum contra motions to strike filed by D. Bergman.
10/07/1988 Post-Hearing Brief of Eastern Natural Gas Company filed by S. Howard.
10/07/1988 Post-Hearing Brief of the PUCO staff, filed by A. Hammer- stein.
09/30/1988 Notice of withdrawal of counsel and designation of new trial attorney filed by D. Bergmann on behalf of OCC.
09/28/1988 Trans., for hearing held on 9/20/88, (KS) Submitted Vol. II, 1-40 pages.
09/15/1988 Trans., for hearing held on 9/6/88, (KS) Con't. Vol. I, 1-52 pages.
09/12/1988 Entry ordering that the hearing will reconvene on 9/20/88, at 10:00 a.m., in the Commission's offices. (AE)
09/06/1988 Joint stipulation and recommendation filed by A. Hammerstein on behalf of the PUCO staff and S. Howard on behalf of applicant.
09/02/1988 Entry granting OCC intervention. (AE)
08/31/1988 Proofs of Publications filed. (Counties/Ashtabula-Trumbull)
08/30/1988 Direct Testimony of Robert Ceisler on behalf of OCC.
08/25/1988 Motion to Intervene filed by D. Nodes on behalf of OCC.
08/05/1988 Management/Performance Audit on behalf of Eastern Natural Gas Company, by Touche Ross.
08/05/1988 Annual Audit on behalf of Eastern Natural Gas Company by Arthur Andersen & Co.
08/03/1988 Entry consolidating this matter with Case No. 88-518-EL-FOR and scheduling a hearing to be held on 9/6/88, at 10:00 a.m., at the offices of the Commission. (AE)
04/27/1988 Entry ordering that Management/Performance Audits of the Gas Purchasing Practices and Policies of Regulated Gas Distribution Companies be conducted in accordance with the provisions of RFP No. U88-GCR-1 pursuant to the Findings of this Entry; Ordering that the cost of the audits be paid by the companies pursuant to the Findings of this Entry.
03/08/1988 Entry scheduling hearing on 9/6/88, at 10:00 a.m., at the offices of the Commission, and ordering company follow directives in the Entry.
01/04/1988 In the Matter of the Regulation of the Purchased Gas Adjustment Clause contained within the Rate Schedules of Eastern Natural Gas Company, and Related Matters.