DIS - Case Record for 20-1678-EL-BGN Skip to main content
      
      
CASE NUMBER: 20-1678-EL-BGN
CASE DESCRIPTION: In the Matter of the Application of Hardin Solar Energy III, LLC for a Certificate of Environmental Compatibility and Public Need to Construct a Solar
DOCUMENT SIGNED ON: 5/3/2024
DATE OF SERVICE: ________________________________________
04/15/2024 Notice of Compliance with Condition 13 – 2024 First Quarter Complaint Summary Report electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
04/03/2024 Notice of Update to Hardin Solar Energy III LLC’s October 31, 2023 Response electronically filed By Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
01/26/2024 Service Notice.
01/25/2024 Administrative Law Judge Entry scheduling a status conference to commence at 10:00 a.m. on March 19, 2024, at the offices of the Commission, 180 East Broad Street, 11th Floor, Hearing Room 11-D, Columbus, Ohio 43215 electronically filed by Debbie S. Ryan on behalf of Jacky Werman St. John, Administrative Law Judge, Ohio Power Siting Board.
01/16/2024 Notice of Compliance with Condition 13 – 2023 Fourth Quarter Complaint Summary Report electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III, LLC.
11/30/2023 Public Comment of Kary Campbell electronically filed by Docketing Staff.
11/13/2023 Comments of Jimmie and Susan Lightner about Hardin Solar's Noncompliance electronically filed by Mr. Jack A. Van Kley on behalf of Lightner, Jimmie and Lightner, Susan.
11/03/2023 Request to be Added to Service List electronically filed by Mr. Jack A. Van Kley on behalf of Jimmie Lightner and Susan Lightner.
11/02/2023 Returned Mail: Entry dated 10/12/23 sent to Hardin Solar Energy, LLC Attn: Christine Pirik, Returned to Sender, Vacant, Unable to Forward.
10/31/2023 Response to September 15, 2023 Lighter Letter electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III, LLC.
10/16/2023 Notice of Compliance with Condition 13 – 2023 Third Quarter Complaint Summary Report electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
10/13/2023 Service Notice.
10/12/2023 Administrative Law Judge Entry that Hardin Solar file a Response to the Lightners’ complaint by October 31, 2023 electronically filed by Ms. Donielle M. Hunter on behalf of Jacky Werman St. John, Administrative Law Judge, Ohio Power Siting Board.
10/04/2023 Public Media Target CD filed in conjunction with public comment on 9-18-23, electronically filed by Docketing Staff on behalf of Docketing.
10/04/2023 Public Media Target: CD filed in conjunction with public comment on 9-18-23, electronically filed by Docketing Staff on behalf of Docketing.
09/22/2023 Notice of Updated Project Contact Information electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
09/18/2023 Public Comment of Jimmie and Susan Lightner filed by Jack Van Kley.
08/21/2023 Public Comment of Jimmie Lee Lightner electronically filed by Docketing Staff.
08/21/2023 Public Comment of Jimmie Lee Lightner electronically filed by Docketing Staff.
07/17/2023 Notice of Compliance with Condition 13– 2023 Second Quarter Complaint Summary Report electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
05/16/2023 Notice of Compliance with Condition 33(b) – State Historic Preservation Office Acceptance of Archaeological Site Avoidance Plan and Commitment to Include on As-Built Specifications electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
04/28/2023 Notice of Compliance with Condition 33(b) – Phase II Archaeological Study and State Historic Preservation Office Concurrence Letter electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
04/17/2023 Notice - Compliance with Condition 13 – 2023 First Quarter Complaint Summary Report electronically filed by Christine M.T. Pirik on behalf of HARDIN SOLAR ENERGY III LLC.
04/12/2023 Notice of Compliance with Condition 33, State Historic Preservation Office Concurrence Letter electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/29/2023 Compliance with Condition 14 - Interconnection Service Agreement and Interconnection Construction Service Agreement electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/22/2023 Notice of Compliance with Condition 2 - Preconstruction Agenda Balance of Plant electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/07/2023 Notice - Compliance with Condition 4 Balance of Plant Civil and Electrical Engineering Drawings (Part 8 of 8) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/07/2023 Notice - Compliance with Condition 4 Balance of Plant Civil and Electrical Engineering Drawings (Part 7 of 8) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/07/2023 Notice - Compliance with Condition 4 Balance of Plant Civil and Electrical Engineering Drawings (Part 6 of 8) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/07/2023 Notice - Compliance with Condition 4 Balance of Plant Civil and Electrical Engineering Drawings (Part 5 of 8) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/07/2023 Notice - Compliance with Condition 4 Balance of Plant Civil and Electrical Engineering Drawings (Part 4 of 8) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/07/2023 Notice - Compliance with Condition 4 Balance of Plant Civil and Electrical Engineering Drawings (Part 3 of 8) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/07/2023 Notice - Compliance with Condition 4 Balance of Plant Civil and Electrical Engineering Drawings (Part 2 of 8) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/07/2023 Notice - Compliance with Condition 4 Balance of Plant Civil and Electrical Engineering Drawings (Part 1 of 8) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
10/06/2022 Notice of Withdrawal of Counsel electronically filed by Ms. Leah Curtis on behalf of Ohio Farm Bureau Federation.
10/06/2022 Notice of Compliance with Condition 9 of Case No. 18-1360-EL-BGN and Condition 14 of Case No. 20-1678-EL-BGN - Interconnection Service Agreement and Interconnection Construction Service Agreement electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy II LLC and Hardin Solar Energy III LLC.
10/06/2022 Notice of Compliance with Condition 18 - Decommissioning Plan and Performance Bond electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/30/2022 Notice - Glare Study - Condition 17 electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/30/2022 Vegetation Management and Landscape Plan – Condition 16 electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/28/2022 Notice of Compliance with Condition 32 - Transportation Management Plan electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III, LLC.
03/18/2022 Compliance with Condition 8 - Storm Water Pollution Prevention Plan electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/17/2022 Notice of Compliance with Condition 5 – Geotechnical Engineering Report electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/17/2022 Notice of Compliance with Conditions 2 and 7 – Preconstruction Agendas and Construction Notices electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/14/2022 Compliance with Condition 19 - Perimeter Fence Design electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III, LLC.
03/02/2022 Notice of Compliance with Condition 4 electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/16/2022 Compliance with Condition 4, Case No. 20-1678-EL-BGN, Tree Clearing Information for Preconstruction Conference electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III, LLC.
09/16/2021 Service Notice.
09/16/2021 Opinion & Order issuing a certificate of environmental compatibility and public need to Hardin Solar Energy III, LLC for the construction, operation, and maintenance of the solar-powered electric generation facility, subject to the conditions set forth in the stipulation and consistent with this Opinion, Order, and Certificate electronically filed by Ms. Mary E. Fischer on behalf of Ohio Power Siting Board.
08/13/2021 Transcript for Public Hearing held 7/13/21@ 6:00 p.m.before the Honorable Megan Addison, Chair Jennifer French, and Jacky Werman St. John at Kenton High School, Hardin Street Kenton, Ohio electronically filed by Ms. Susan Ingraham on behalf of Midwest Reporting Service and Ms. Susan Ingraham.
08/06/2021 Transcript for hearing held on July 29, 2021 at 10;00 a.m. at the offices of the Public Utilities Commission of Ohio, 180 E. Broad Street, Hearing Room 11-C, Columbus, OH before Administrative Law Judges Megan Addison and Jacky St. John electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Mr. Michael O. Spencer.
07/26/2021 Notice - Compliance with Joint Stipulation and Recommendation Condition 33 – Supplement to Archaeological Report electronically filed by Christine M.T. Pirik on behalf of HARDIN SOLAR ENERGY III LLC.
07/26/2021 Prefiled Testimony of James S. O'Dell on Behalf of the Staff of the Public Utilities Commission of Ohio, Power Siting Department electronically filed by Mrs. Kimberly M. Naeder on behalf of OPSB.
07/21/2021 Direct Testimony and Exhibits of Ryan Van Portfliet electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
07/21/2021 Joint Stipulation and Recommendation electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
07/19/2021 Proof of Publication and Service of Procedural Schedule and Accepted, Complete Application electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III, LLC.
07/13/2021 Service Notice,
07/13/2021 Administrative Law Judge Entry granting the motion to intervene of the Ohio Farm Bureau Federation electronically filed by Ms. Mary E Fischer on behalf of Jacky Werman St. John, Administrative Law Judge, Ohio Power Siting Board.
06/28/2021 Service Notice.
06/28/2021 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
06/28/2021 Public Comment of John H. Conkle, via website, electronically filed by Docketing Staff.
06/23/2021 Service Notice
06/23/2021 Administrative Law Judge Entry converting the local public hearing and the adjudicatory hearing to in-person hearings in accordance with Paragraphs 22 and 23 and requiring applicant to publish notice of the same electronically filed by Ms. Mary E. Fischer on behalf of Megan J. Addison, Administrative Law Judge, Ohio Power Siting Board.
06/21/2021 Response to Seventh Data Request from Staff of the Ohio Power Siting Board electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
06/10/2021 Public Comment of Doris Engler, via website, electronically filed by Docketing Staff.
06/10/2021 Public Comment of Doris Engler, President of Keith Farms, Inc., via website, electronically filed by Docketing Staff.
06/10/2021 Response to Fifth Data Request from Staff of the Ohio Power Siting Board electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
06/09/2021 Public Comment of Denver Nelson, via website, electronically filed by Docketing Staff.
06/08/2021 Public Comment of concerned consumer, via website. electronically filed by Docketing Staff.
06/03/2021 Motion and Memorandum in Support, to Intervene of Ohio Farm Bureau Federation electronically filed by Amy M Milam on behalf of Ohio Farm Bureau Federation.
06/02/2021 Response to 6th data request from OPSB Staff electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
06/01/2021 Public Comment of Raymond Hipsher, via website, electronically filed by Docketing Staff.
06/01/2021 Public Comment of Concerned Citizens, via website, electronically filed by Docketing Staff.
05/24/2021 Proof of Pub and Service of Procedural Schedule and Accepted, Complete Application electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
05/24/2021 Public Comment of Concerned Citizens, via website, electronically filed by Docketing Staff.
05/19/2021 Response to Fourth Data Request from Staff of the Ohio Power Siting Board electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
05/18/2021 Public Comment by Don and Nikki Staup, via website, electronically filed by Docketing Staff.
05/17/2021 Public Comment of a Concerned Citizen, via website, electronically filed by Docketing Staff.
05/13/2021 Public Comment of Melissa Carl, via website, electronically filed by Docketing Staff.
05/04/2021 Public Comment of Heather Moran, via website, electronically filed by Docketing Staff.
04/30/2021 Public Comment of Heather Moran, via website, electronically filed by Docketing Staff.
04/30/2021 Public Comment of Ryan Moran, via website, electronically filed by Docketing Staff.
04/27/2021 Service Notice.
04/26/2021 Administrative Law Judge Entry ordering the hearings in this matter be scheduled in accordance with Paragraph 19; ordering that the notice of the Application and hearings be published by Hardin Solar in accordance with Paragraphs 21, 22, 25, and 26; ordering that witness registration occur pursuant to Paragraphs 23, 27, and 28 and ordering that the parties observe the filing deadlines set forth in Paragraph 33 electronically filed by Kelli C. King on behalf of Jacky Werman St. John, Administrative Law Judge, Ohio Power Siting Board.
04/20/2021 Notice of Application Fee Payment electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
04/19/2021 Response to Third Data Request from Staff of the Ohio Power Siting Board electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
04/14/2021 Public Comment of Robert Anthony, via website, electronically filed by Docketing Staff.
04/13/2021 Notice of Certificate of Service of Accepted, Complete Application on Local Public Officials and Libraries electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
04/13/2021 Response to Second Data Request from Staff of the Ohio Power Siting Board electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
04/13/2021 Second Supplement to Application – Viewshed Analysis Addendum 1 – O.A.C. 4906-4-08(D)(4) 5-mile Map electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
04/12/2021 Letter regarding application completeness electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
03/24/2021 Public Comment of Robert Anthony, via website, electronically filed by Docketing.
03/18/2021 Service Notice.
03/18/2021 Entry granting the request to transfer 20 megawatts and a portion of the certificated project area held by Hardin Solar Energy II LLC to Hardin Solar Energy III LLC, in accordance with R.C. 4906.04. electronically filed by Ms. Mary E Fischer on behalf of Ohio Power Siting Board.
03/17/2021 Public Comment of Mark Runkle, via website, electronically filed by Docketing Staff.
03/12/2021 Response to First Data Request from Staff of the Ohio Power Siting Board electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
03/05/2021 Service Notice.
03/05/2021 Administrative Law Judge Entry granting the motion for waivers and motion for protective order filed by Hardin Solar Energy III LLC electronically filed by Ms. Mary E Fischer on behalf of Jacky Werman St. John, Administrative Law Judge, Ohio Power Siting Board.
02/26/2021 Correspondence Regarding Motion for Wavier electronically filed by Mrs. Kimberly M Naeder on behalf of OPSB.
02/19/2021 Application - Supplement to Application – Architectural Resources Survey, State Historic Preservation Office Concurrence electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/12/2021 Public Comment of Gary and Karen Harpster, via website electronically filed by Docketing Staff.
02/11/2021 Motion for Waiver and Memorandum in Support electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Motion for Protective Order and Memorandum in Support electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 34 of 34 (Exhibit AA - Drainage Tile Assessment and Construction Impact Report) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 33 of 34 (Exhibit Z - Viewshed Analysis and Aesthetic Resources Inventory) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 32 of 34 (Exhibit Y - Architectural Resources Survey) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 31 of 34 (Exhibit X - Management Summary: Phase I Archaeological Investigations) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 30 of 34 (Exhibit W - Programmatic Agreement) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 29 of 34 (Exhibit V - Vegetation Management and Landscape Plan) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 28 of 34 (Exhibit U - Directionally Drilled Installations Inadvertent Return Plan) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 27 of 34 (Exhibit T - Ohio Department of Natural Resources Communication) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 26 of 34 (Exhibit S - U.S. Fish and Wildlife Service Communication) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 25 of 34 (Exhibit R – Part 3 of 3 - Glare Analysis) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 24 of 34 (Exhibit R – Part 2 of 3 - Glare Analysis) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 23 of 34 (Exhibit R – Part 1 of 3 - Glare Analysis) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 22 of 34 (Exhibit Q - Preliminary Geotechnical Engineering Report) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 21 of 34 (Exhibit P –Pre-construction Noise Analysis) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 20 of 34 (Exhibit O - Decommissioning Plan) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 19 of 34 (Exhibit N - Certificate of Liability Insurance) electronically filed by Christine M.T. Pirik on behalf of HARDIN SOLAR ENERGY III LLC.
02/11/2021 Confidential Document Target: Application Narrative, Exhibits K&N filed by Dickinson Wright PLLC on behalf of Hardin Solar Energy III, LLC. (10 pages)
02/11/2021 Application 18 of 34 (Exhibit M - Start of Construction and Start of Operations Notices) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 17 of 34 (Exhibit L - Complaint Resolution Plan) electronically filed by Christine M.T. Pirik on behalf of Hardin Energy Solar III LLC.
02/11/2021 Application - 16 of 34 (Exhibit K - Economic Impact and Land Use Analysis) electronically filed by Christine M.T. Pirik on behalf of Hardin Energy Solar III LLC.
02/11/2021 Application - 15 of 34 (Exhibit J - Property Value Impact Study) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 14 of 34 (Exhibit I – Community Engagement and Outreach Plan) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 13 of 34 (Exhibit H - PJM Interconnection Studies) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 12 of 34 (Exhibit G – Part 2 of 2 - Wetlands and Other Waters of the U.S. Delineation Report) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 11 of 34 (Exhibit G – Part 1 of 2 - Wetlands and Other Waters of the U.S. Delineation Report) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application - 10 of 34 (Exhibit F - Site Characterization Survey Report) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application 9 of 34 (Exhibit E - Part 2 of 2 - Road Condition Report) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application 8 of 34 (Exhibit E - Part 1 of 2 - Road Condition Report) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application 7 or 34 (Exhibit D - Substation Transformer Specifications) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application 6 of 34 (Exhibit C - Inverter Specifications) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application 5 of 34 (Exhibit B - Tracking System Specifications) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application 4 of 34 (Exhibit A - Module Specifications) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application 3 of 34 (Figures ending in 08-8) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application 2 of 34 (Figures beginning with 03-1) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
02/11/2021 Application 1 of 34 (Cover, Affidavit, and Narrative) electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
01/27/2021 Public Comment of Holli Underwood on behalf of Hardin County Chamber & Business Alliance, via website, electronically filed by Docketing Staff.
01/04/2021 Proof of Publication for Public Information Meeting electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
12/21/2020 Public Comment of Pearlann Pohlman, via website, electronically filed by Docketing Staff.
12/15/2020 Public Comment of Tim Scarbrough, via website, electronically filed by Docketing Staff.
12/15/2020 Public Comment of Jody Scarbrough, via website, electronically filed by Docketing Staff.
12/15/2020 Notice of Compliance with Service Requirement for Public Information Meetings and Service List electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
12/15/2020 Preapplication Notification Letter electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.
11/20/2020 Service Notice. (Electronically Served)
11/20/2020 Administrative Law Judge Entry granting the motion for waiver electronically filed by Ms. Mary E Fischer on behalf of Jacky Werman St. John, Administrative Law Judge, Ohio Power Siting Board.
11/18/2020 Correspondence Regarding Motion for Wavier electronically filed by Mrs. Kimberly M Naeder on behalf of OPSB.
11/12/2020 In the Matter of the Motion for Waiver and Request for Approval of an Alternative Method for the Public Information Meeting Request for Expedited Ruling and Memorandum in Support electronically filed by Christine M.T. Pirik on behalf of Hardin Solar Energy III LLC.