DIS - Case Record for 20-1277-EL-BLN Skip to main content
      
      
CASE NUMBER: 20-1277-EL-BLN
CASE DESCRIPTION: Licking Co-Op Extension – Apple Valley 138 kV Transmission Line Project
DOCUMENT SIGNED ON: 5/7/2024
DATE OF SERVICE: ________________________________________
03/22/2021 Notice of In-Service Date for the Licking Co-Op Extension – Apple Valley 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company.
12/16/2020 Construction Start Notice electronically filed by Tanner Wolffram on behalf of Ohio Power Company.
12/04/2020 Proof of Compliance with Condition (2) and associated exhibit for Apple Valley 138 kV Switch Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company.
11/16/2020 Service Notice.
11/16/2020 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
09/02/2020 Proof of Compliance associated exhibits for the Licking Co-Op Extension – Apple Valley 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company.
08/24/2020 Letter of Notification Application for the Licking Co-Op Extension- Apple Valley 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company.
08/17/2020 In the Matter of the Pre-Application Notification Letter for the Licking Co-Op Extension – Apple Valley 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company.