06/08/2020
|
Notice of In-Service Date and Construction Completion Date as of May 27, 2020 for the Vine-City of Columbus West 138 kV Pole Replacement Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
05/21/2020
|
Service Notice. |
05/21/2020
|
Opinion & Order approving the accelerated applications in the above-captioned proceedings for certificates to construct various transmission line projects and for a natural gas pipeline reroute project. electronically filed by Ms. Mary E Fischer on behalf of Ohio Power Siting Board. |
05/14/2020
|
Service Notice |
05/14/2020
|
Administrative Law Judge Entry granting limited certificate authority. electronically filed by Ms. Mary E. Fischer on behalf of Jeffrey R. Jones, Administrative Law Judge, Ohio Power Siting Board. |
04/29/2020
|
Service Notice |
04/29/2020
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
04/20/2020
|
Notice Proof of Compliance Letter and associated exhibits for the Vine-City of Columbus West 138 kV Pole Replacement Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
04/14/2020
|
Notice Construction for the Vine-City of Columbus West 138 kV Pole Replacement Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
03/03/2020
|
In the matter of the Pre-Application Notification Letter for the Vine-City of Columbus West 138kV Pole Replacement Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |