03/18/2021 Cumminsville 5B Rebuild Project Notification of Completion of Construction and In-Service Date electronically filed by Carys Cochern on behalf of Duke Energy Ohio, Inc.
06/26/2020 Correspondence of Habitat Summary relating to the Indiana and northern long-eared bat habitat electronically filed by Carys Cochern on behalf of Duke Energy.
05/21/2020 Service Notice.
05/21/2020 Opinion & Order approving the accelerated applications in the above-captioned proceedings for certificates to construct various transmission line projects and for a natural gas pipeline reroute project. electronically filed by Ms. Mary E Fischer on behalf of Ohio Power Siting Board.
05/08/2020 Duke Energy Ohio, Inc.'s Supplemental Response to Staff Data Request 01-003 electronically filed by Carys Cochern on behalf of Duke Energy.
05/08/2020 Duke Energy Ohio, Inc.'s Supplemental Response to Staff Data Request 01-003 electronically filed by Carys Cochern on behalf of Duke Energy.
05/06/2020 Service Notice
05/06/2020 Duke Energy Ohio, Inc. Cumminsville 5B Rebuild Project Letter Accepting Condition for Approval electronically filed by Carys Cochern on behalf of Duke Energy.
05/05/2020 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
05/05/2020 Duke Energy Ohio, Inc.'s Response to Staff Data Request 01-003 electronically filed by Carys Cochern on behalf of Duke Energy.
05/05/2020 Duke Energy Ohio, Inc.'s Response to Staff Data Request 01-002 electronically filed by Carys Cochern on behalf of Duke Energy.
05/05/2020 Duke Energy Ohio, Inc.'s Response to Staff Data Request 01-001 electronically filed by Carys Cochern on behalf of Duke Energy.
05/05/2020 Duke Energy Ohio, Inc.'s Response to Staff Data Request 01-001 electronically filed by Carys Cochern on behalf of Duke Energy.
02/18/2020 Proof of Publication of Cumminsville 5B Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy.
02/13/2020 Notice of Proof of Service for the Duke Energy Ohio, Inc. Cumminsville 5B Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy.
02/11/2020 Application of Duke Energy Ohio, Inc. for the Cumminsville 5B Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy.
02/11/2020 Letter of Notification Application of Duke Energy Ohio, Inc. for the Cumminsville 5B Rebuild Project electronically filed by Carys Cochern on behalf of Duke Energy.
01/31/2020 In the matter of the Pre-Application Notification Letter for I-74/I-75 Interchange Reconstruction Project electronically filed by Carys Cochern on behalf of Duke Energy.