CASE NUMBER: 19-1775-EL-BNR
CASE DESCRIPTION: AEP Ohio Transmission Company, Inc.
DOCUMENT SIGNED ON: 5/6/2024
DATE OF SERVICE: ________________________________________
11/24/2020 Notification of In-Service Date and Construction Completion Date of 11/20/20 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
05/01/2020 Notification of In-Service Date and Construction Completion Date for the Willow Island- Mill Creek 138 kV Transmission Line Extension Project #4 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
01/22/2020 Notice of start of construction for the Willow Island-Mill Creek 138 kV Transmission Line Extension Project #4 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
10/04/2019 Service Notice.
10/04/2019 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
09/25/2019 Proof of Compliance Letter and associated exhibits for the Willow Island- Mill Creek 138 kV Transmission Line Extension Project #4 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
09/19/2019 Construction Notice for the Willow Island- Mill Creek 138 kV Transmission Line Extension Project #4 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
09/12/2019 In the matter of the Pre-Application Notification Letter electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.