DIS - Case Record for 19-1613-EL-BLN Skip to main content
      
      
CASE NUMBER: 19-1613-EL-BLN
CASE DESCRIPTION: Barnesville-Summerfield 138kV Transmission Line Project
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
08/29/2019 Service Notice.
08/29/2019 Notice of Proof of Compliance electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
08/29/2019 Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB.
08/28/2019 Notice of Proof of Compliance and Associated Exhibits for the Barnesville-Summerfield electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
08/22/2019 Letter of Notification for the Barnesville-Summerfield 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
08/21/2019 In the Matter of the Pre-Application Notification letter electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.