12/23/2019 Notice of Completion of Construction filed by R. Maggiore on behalf of FirstEnergy Service Company.
09/20/2019 Service Notice (Staff Report)
09/20/2019 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
08/09/2019 Application of American Transmission Systems, Inc. for Galion-Roberts South 138 kV Line Switch Replacement Project filed by R. Maggiore.
07/22/2019 In the Matter of the Pre-Application Notification Letter electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc.