11/22/2019 | Notice of Construction Start Date electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
10/17/2019 | Service Notice | 2 |
10/17/2019 | Order on Certificate that the Ohio Power Siting Board grants the application filed by AEP Ohio Transmission Company, Inc. to amend its certificate. | 10 |
10/08/2019 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 7 |
10/08/2019 | Service Notice | 4 |
10/01/2019 | Notice of Proof of Compliance Letter and associated exhibits for the Amendment to the Barnesville-Summerfield Project. electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 82 |
08/21/2019 | Request to Withdraw Shift 2 and the Revised Amended Application electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 45 |
05/29/2019 | In the Matter of the Application of AEP Ohio Transmission Company,
Inc. for Amendment to the Certificate of Environmental Compatibility
and Public Need for the Barnesville-Summerfield 138 kV Transmission
Line Rebuild Project electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Company, Inc. | 47 |