10/17/2019 Service Notice
10/17/2019 Entry that the Ohio Power Siting Board dismisses this matter at the request of the applicant, AEP Ohio Transmission Company, Inc.
09/12/2019 Notice of Withdrawal of the Willow Island- Mill Creek 138 kV Transmission Line Extension Project #2. electronically filed by Tanner Wolffram on behalf of Ohio Power Company.
08/29/2019 Service Notice.
08/29/2019 Notice of Correction to the Construction Notice for the Willow Island-Mill Creek Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company.
08/29/2019 Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB.
06/06/2019 Construction Notice for Willow Island-Mill Creek 138 kV Transmission Line Extension Project #2 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Company, Inc.
04/22/2019 In the Matter of the Pre-Application Notification Letter electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.