12/27/2021
|
Construction Completion Notification Letter electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
07/14/2020
|
Notice of the Start of Construction of Project will commence on July 20, 20202 electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
08/15/2019
|
Notice of the Filing of Supplemental Information in Response to Staff Request electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
08/15/2019
|
Service Notice |
08/14/2019
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
05/29/2019
|
Proof of Pub of Public Notice of Project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |
05/22/2019
|
Application of ATSI for the Darrow Substation Expansion Project filed by N. Bryksenkova. |
04/04/2019
|
In the matter of the Pre-application Notification Letter for Darrow Substation Expansion Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |