01/28/2020
|
Case Action Form Closing Case as of 1/28/20 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio. |
01/16/2020
|
Service Notice |
01/16/2020
|
Entry that the Ohio Power Siting Board dismisses this matter at the request of the applicant, American Transmission Systems, Incorporated electronically filed by Docketing. |
11/13/2019
|
Notice of Cancellation of Project filed by M. Hunsche on behalf of FirstEnergy Service Company and American Transmission Systems, Inc. |
04/18/2019
|
Service Notice. |
04/18/2019
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
04/08/2019
|
Notification of the Submittal of Supplemental Information electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
04/03/2019
|
Construction Notice of FirstEnergy Service Company for Mayfield-Eastlake Q-3 & Q-4 138 kV Transmission Line Tap to Nathan Substation Project filed by W. Beutler. |
01/23/2019
|
In the Matter of the Pre-Application Notification Letter for the Mayfield-Eastlake Q-3 & Q-4 138 kV Transmission Line Tap to Nathan Substation Project filed by W. Beutler on behalf of FirstEnergy Transmission Company. |