DIS - Case Record for 19-0149-EL-BNR Skip to main content

Case Record For:

19-0149-EL-BNR

File a Public Comment
Case Title: Mayfield-Eastlake Q-3 & Q-4 138 kV Transmission Line Tap to Nathan Substation Project
Status: CL-CLOSED
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 1/23/2019
Date Closed: 1/28/2020
Printable Docket Card Service List
View per page
Date FiledSummaryPages
01/28/2020Case Action Form Closing Case as of 1/28/20 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio.2
01/16/2020Service Notice1
01/16/2020Entry that the Ohio Power Siting Board dismisses this matter at the request of the applicant, American Transmission Systems, Incorporated electronically filed by Docketing.4
11/13/2019Notice of Cancellation of Project filed by M. Hunsche on behalf of FirstEnergy Service Company and American Transmission Systems, Inc.1
04/18/2019Service Notice.3
04/18/2019Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.5
04/08/2019Notification of the Submittal of Supplemental Information electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.2
04/03/2019Construction Notice of FirstEnergy Service Company for Mayfield-Eastlake Q-3 & Q-4 138 kV Transmission Line Tap to Nathan Substation Project filed by W. Beutler.45
01/23/2019In the Matter of the Pre-Application Notification Letter for the Mayfield-Eastlake Q-3 & Q-4 138 kV Transmission Line Tap to Nathan Substation Project filed by W. Beutler on behalf of FirstEnergy Transmission Company.1