12/28/2020
|
Notification Construction Completion Date as of December 9, 2020 for the Gemini Station 138kV Substation Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
09/13/2019
|
Notification of PJM Identifier for the Adjustment electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
08/01/2019
|
Notification of Start of Construction for the Gemini Station 138 kV Substation Project. electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Company. |
12/18/2018
|
Correspondence for Acceptance of Staff Conditions electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
12/13/2018
|
Notice (Proof of Compliance) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
12/11/2018
|
Service Notice |
12/11/2018
|
Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB. |
11/19/2018
|
Letter of Notification electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
11/13/2018
|
In the matter of the (Pre-Application Notification Letter) electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |