DIS - Case Record for 18-0292-RR-FED Skip to main content

Case Record For:

18-0292-RR-FED

File a Public Comment
Case Title: In the Matter of a Request for Upgrades to the Active Warning Devices at Eight CSX Transportation, Inc. Crossings in Marion County, Ohio.
Status: CL-CLOSED
Industry Code: RR-RAILROAD
Purpose Code: FED-Federally funded warning projects
Date Opened: 2/15/2018
Date Closed: 7/28/2022
Printable Docket Card Service List
View All
1 - 11 of 11 documents 1 /  1 
Date FiledSummaryPages
07/29/2022Memo Closing Case In the Matter of a Request for Upgrades to the Active Warning Devices at Eight CSX Transportation, Inc. Crossings, in Marion County, Ohio. electronically filed by Mr. Thomas Persinger on behalf of PUCO/Rail Division.17
07/28/2022Case Action Form closing case with an effective date of 7/28/22. In the Matter of a Request for Upgrades to the Active Warning Devices at Eight CSX Transportation, Inc. Crossings in Marion County, Ohio electronically filed by Mr. Thomas Persinger on behalf of PUCO/Rail Division.2
08/29/2019Notification by City of Marion for Approval of Redesign for Marion Corridor Project electronically filed by Mrs. Nicole S. Henning on behalf of CSX Transportation.4
05/01/2019Service Notice2
05/01/2019Entry ordering that Staff's request to place the project completion date in abeyance is granted and that CSX shall as soon as possible file notice in the docket of approval of the project redesign by the City of Marion; within 60 days of the approval by the city of Marion, CSX begins its work on the project.4
04/03/2019Response In the Matter of an Extension Request for Upgrades to the Active Warning Devices at Eight CSX Transportation, Inc. Crossings in Marion County, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division.7
03/25/2019Request of Marion, Marion Co., OH, Corridor Project for 6 months extension electronically filed by Mrs. Nicole S Henning on behalf of CSX Transportation.6
04/04/2018Finding and ordered, That by May 4, 2018, CSX file notice that it has initiated with OEC, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossings as set forth in Paragraph 8. It is, further, ordered, That CSX follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the projects by April 4, 2019.6
04/04/2018Service Notice2
03/01/2018Utility Notifications for Eight Crossings in Marion OH. electronically filed by Mrs. Nicole S Henning on behalf of CSX Transportation.2
02/15/2018In the Matter of a Request for Upgrades to the Active Warning Devices at Eight CSX Transportation, Inc. Crossings in Marion County, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division.233
 
1 /  1 
      
      
Attorney General:
Attorney Examiner:
Lynn, James