CASE NUMBER: 17-2199-RR-FED
CASE DESCRIPTION: In the Matter of a Request for an Upgrade to the Active Warning Devices at the Norfolk Southern Railway Crossing, S. Munson Road DOT#509-484C, in Fult
DOCUMENT SIGNED ON: 4/23/2024
DATE OF SERVICE: ________________________________________
04/29/2020 Case action form with an effective date of 4/29/2020 In the Matter of an Extension Request for an Upgrade to the Active Warning Devices at the Norfolk Southern Railway Crossing, S. Munson Road DOT#509-484C, in Fulton County, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division.
04/29/2020 Memo closing case: In the Matter of an Extension Request for an Upgrade to the Active Warning Devices at the Norfolk Southern Railway Crossing, S. Munson Road DOT#509-484C, in Fulton County, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division.
09/20/2018 Service Notice
09/19/2018 Entry ordered, That NS's request for additional time to complete the project be granted in accordance with Paragraph 9. It is, further, That NS complete the project no later than November 15, 2018.
08/28/2018 Response memo recommending the 90 day extension request but would like it completed by November 15, 2018 electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division.
08/17/2018 Amended Request to Defer Construction Deadline electronically filed by Mr. D. Casey Talbott on behalf of Norfolk Southern Railway Company.
08/07/2018 Request to Defer Construction Deadline electronically filed by Mr. D. Casey Talbott on behalf of Norfolk Southern Railway Company.
12/21/2017 Utility Notice electronically filed by Mr. D. Casey Talbott on behalf of Norfolk Southern Railway Company.
11/21/2017 Service Notice
11/21/2017 Finding and Order that by December 21, 2017 NS file notice that it has initiated with TEC or any applicable utility the process to ensure that electric service will be available at the involved grade crossing as set forth in Paragraph 8 and tha NS follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by August 21, 2018.
10/25/2017 In the Matter of a Request for an Upgrade to the Active Warning Devices at the Norfolk Southern Railway Crossing, S. Munson Road DOT#509-484C, in Fulton County, Ohio. electronically filed by Mrs. Jill A Henry on behalf of PUCO/Rail Division.