CASE NUMBER: 17-1954-EL-BNR
CASE DESCRIPTION: Brookside-Longview West 138 kV Transmission Line Temporary Bypass Project
DOCUMENT SIGNED ON: 5/1/2024
DATE OF SERVICE: ________________________________________
08/09/2019 Case Action Form Close Cases as of 8/9/2019 electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio.
12/11/2017 Construction Notice to advised that construction on this Project, which was approved by the Board on October 10, 2017, was completed on December 1, 2017 filed by Scott Humphrys on behalf of FirstEnergy Services Company.
10/03/2017 Service Notice
10/03/2017 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of the Staff of the OPSB.
09/25/2017 Application for the construction notice of Brookside-Longview West 138kV Transmission Line Temporary Bypass Project filed by S. Humphrys on behalf of FirstEnergy Service Co.
09/08/2017 In the matter of the Filing of Pre-Application Letter electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.