04/20/2023 Notice that the transaction involving transfer of the Guernsey Power Station Electrical Interconnection is closed electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.
01/20/2022 Service Notice.
01/20/2022 Entry granting the joint application to bifurcate the construction certificate and transfer the portion of the construction certificate for a utility switchyard from Guernsey Power Station, LLC to Ohio Power Company in accordance with R.C. 4906.04. electronically filed by Ms. Mary E. Fischer on behalf of Ohio Power Siting Board.
08/27/2021 Joint Application to Bifurcate, Clarify, and Transfer Certificate electronically filed by Ms. Christen M. Blend on behalf of Ohio Power Company.
10/02/2020 Correspondence of Guernsey Power Station, LLC in Compliance with Staff Report Condition No. 7 - Updated Streamside Vegetation Restoration Plan electronically filed by Teresa Orahood on behalf of Dylan F. Borchers.
09/28/2020 Correspondence of Guernsey Power Station, LLC in Compliance with Certificate Condition No. 6 and LON Condition No. 1 - Updated 401 and 404 Permits electronically filed by Teresa Orahood on behalf of Dylan F. Borchers.
05/22/2020 Correspondence of Guernsey Power Station, LLC in Compliance with Staff Report Condition No. 1 electronically filed by Teresa Orahood on behalf of Dylan F. Borchers.
10/28/2019 Case Action Form reflecting address change electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
10/25/2019 Notice of material change filed by M Garber on behalf of Guernsey Power Station, LLC.
08/09/2019 Correspondence of Guernsey Power Station, LLC in Compliance with Staff Report Condition No. 7 electronically filed by Teresa Orahood on behalf of Dylan F. Borchers.
08/05/2019 Notice Guernsey Power Station, LLC of the Start of Construction electronically filed by Teresa Orahood on behalf of Dylan F. Borchers.
08/02/2019 Correspondence of Guernsey Power, LLC in Compliance with Staff Report Condition No. 1 electronically filed by Teresa Orahood on behalf of Dylan F. Borchers.
07/29/2019 Notice of compliance with Staff Report Condition No. 1 electronically filed by Teresa Orahood on behalf of Dylan F. Borchers.
09/19/2018 Notice of compliance of Guernsey Power Station, LLC in regarding Staff Report Condition No. 1 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.
01/05/2018 Correspondence of Guernsey Power Station, LLC in Compliance with Staff Report Condition No. 8 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.
12/11/2017 Correspondence of Guernsey Power Station, LLC in Compliance with Staff Report Condition No. 6 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.
12/08/2017 Guernsey Power Station, LLC’s Supplement to Letter of Notification electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.
12/04/2017 Service Notice
12/01/2017 Staff Report of Investigation electronically filed by Adam Bargar on behalf of PUCO Staff.
12/01/2017 Letter of Notification for Guernsey Power Station Electrical Interconnection to correct an inadvertent error in Letter of Notification filed September 8, 2017 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.
09/19/2017 Proof of Pub electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield. (Guernsey and Noble Counties)
09/15/2017 Guernsey Power Station, LLC's Proof of Service electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.
09/08/2017 Letter of Notification of Guernsey Power Station for Guernsey Power Station Electrical Interconnection - Part 4 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.
09/08/2017 Letter of Notification of Guernsey Power Station for Guernsey Power Station Electrical Interconnection - Part 3 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.
09/08/2017 Letter of Notification of Guernsey Power Station for Guernsey Power Station Electrical Interconnection - Part 2 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.
09/08/2017 Letter of Notification of Guernsey Power Station for Guernsey Power Station Electrical Interconnection - Part 1 electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.
08/24/2017 In the Matter of Guernsey Power Station, LLC’s Pre-application letter for the Guernsey Power Station Electrical Interconnection electronically filed by Teresa Orahood on behalf of Sally W. Bloomfield.