CASE DESCRIPTION: London-Tangy 138 kV Transmission Line Relocation and Tangy Substation Expansion Project
DOCUMENT SIGNED ON: 5/24/2024
DATE OF SERVICE: ________________________________________
12/19/2018 Notice that construction on both projects was completed on December 3, 2018 filed on W. Beutler on behalf of FirstEnergy Service Company.
04/13/2018 Correspondence providing supplemental information concerning an engineering change to the the construction of the London-Tangy 138 kV Transmission Line Relocation and Tangy Substation Expansion Project filed on behalf of FirstEnergy Service Company by W. Beutler.
09/11/2017 Construction Notice that project will commence on September 18, 2017 filed by W. Beutler on behalf of FirstEnergy Service Company.
08/24/2017 Service Notice
08/24/2017 Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB.
06/01/2017 Construction Notice for the London-Tangy 138 kV Transmission Line Relocation and Tangy Substation Expansion Project filed on behalf of FirstEnergy Service Company by W. Beutler.
05/25/2017 In the matter of the pre-application notification letter for the London-Tangy 138 kV Transmission Line Relocation And Tangy Substation Expansion Project.