CASE NUMBER: 17-1241-EL-BNR
CASE DESCRIPTION: Jackman-GM Powertrain 138kV Transmission Line Project
DOCUMENT SIGNED ON: 4/25/2024
DATE OF SERVICE: ________________________________________
09/03/2019 Case Action Form to Close Case with an effective date of 9/3/19, electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio.
01/11/2018 Notice advising that Construction on 138 kV Structure Addition to GM Powertrain Transmission Lines Substation Project was completed on January 7, 2018 filed by N. Bryksenkova on behalf of FirstEnergy Service Company.
06/12/2017 Construction Notice advising of June 16, 2017 start date filed on behalf of FirstEnergy Service Company by N. Bryksenkova.
06/02/2017 Service Notice
06/02/2017 Staff Report of Investigation electronically filed by Adam Bargar on behalf of Staff of OPSB.
05/19/2017 Construction Notice and Application for a Certificate of Environmental Compatibility and Public Need for the 138kV Structure Addition to GM Powertrain Transmission Line Substation Project (Part 2 of 2) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
05/19/2017 Construction Notice and Application for a Certificate of Environmental Compatibility and Public Need for the 138kV Structure Addition to GM Powertrain Transmission Line Substation Project (Part 1 of 2) electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.
05/12/2017 Pre-Application Notice Letter for Jackman-GM Powertrain Transmission Line Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.