09/11/2023
|
Notice of Substitution of Counsel electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
01/07/2021
|
Notice of Substitution of Counsel electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
10/31/2019
|
Notice of the Completion of Construction of Project was May 29, 2019 electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
02/22/2018
|
Letter of Notification that project commenced on July 10, 2017 filed by S.M. Humphrys on behalf of FirstEnergy Service Company. |
07/07/2017
|
Service Notice |
07/07/2017
|
Service Notice |
07/06/2017
|
Entry Order on Certificate stating that the application filed by ATSI to amend the certificate of environmental compatibility and public need issued in the Hayes-West Fremont Case for Hayes-West Fremont 138kV transmission line project be granted, as described in this Order and subject to conditions set forth in the Hayes-West Fremont Case, 16-1593-EL-BTA, 16-1594-EL-BTA, 16-1595-EL-BTA, and this Order. |
05/19/2017
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
05/19/2017
|
Service Notice |
04/26/2017
|
Proof of publication filed by Scott M. Humphrys on behalf of FirstEnergy Service Company. |
04/12/2017
|
Application of Amendment Four to the Hayes-West Fremont 138kV Transmission Line Project filed by S. Humphrys on behalf of FirstEnergy Service Company. |
04/06/2017
|
In the Matter of the Pre-Application Notification Letter - Amendment Four to the the Hayes-West Fremont 138 kV Transmission Line Project filed by S. Humphrys on behalf of FirstEnergy Service Company. |