DIS - Case Record for 17-0813-EL-BLN Skip to main content
      
      
CASE NUMBER: 17-0813-EL-BLN
CASE DESCRIPTION: Ware Road-Seaman 138kV Transmission Line Rebuild Project
DOCUMENT SIGNED ON: 4/19/2024
DATE OF SERVICE: ________________________________________
12/11/2018 Notice of Start of Construction electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.
08/02/2017 Correspondence Accepting All Staff Conditions Contained in Staff Report electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
07/28/2017 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
07/28/2017 Service Notice
05/23/2017 Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/23/2017 Public Comment electronically filed by Docketing Staff on behalf of Docketing.
05/16/2017 Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/16/2017 Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 15) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 14) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 13) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 12) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 11) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 10) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 9) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 8) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 7) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 6) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 5) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 4) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 3) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 Letter of Notification (Part 2) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
05/05/2017 In the matter of the Letter of Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.