DIS - Case Record for 16-1993-EL-BLN Skip to main content
      
      
CASE NUMBER: 16-1993-EL-BLN
CASE DESCRIPTION: Britton-Davidson 138kV Transmission Line Project
DOCUMENT SIGNED ON: 5/20/2024
DATE OF SERVICE: ________________________________________
09/16/2019 Case Action Form Close Case electronically filed by Ms. Mary E Fischer on behalf of Jeffrey R. Jones, Attorney Examiner, Public Utilities Commission of Ohio.
11/09/2017 Notification electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc.
11/16/2016 Correspondence re Commencement of Construction electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company.
11/08/2016 Correspondence electronically filed by Mrs. Erin C Miller on behalf of AEP Ohio Transmission Company.
11/07/2016 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
10/28/2016 Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company (Franklin Co.)
10/27/2016 Public Comment in opposition filed on behalf of concerned consumer electronically filed by Ms. Donielle M Hunter on behalf of PUCO Staff
10/21/2016 Notification - Public Notification Compliance Filing (Britton-Davidson) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
10/21/2016 Notification - Official Notification Compliance Filing (Britton-Davidson) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company.
10/19/2016 Motion to intervene the Letter of Notification referenced in The Columbus Dispatch, October 12, 2016, filed on behalf of Diane and Jeff Overdorff.
10/19/2016 Public Comment in opposition expressing concern of the location of the facility filed by Liz Bauer electronically filed by Ms. Donielle M Hunter on behalf of PUCO Staff
10/17/2016 Public comment expressing concern over the Britton-Davidson 138-kV Transmission Line project filed by M. Hogan.
10/17/2016 Public comment expressing concern over the Britton-Davidson 138-kV Transmission Line Project filed by S. Stanton.
10/14/2016 Public Comment in opposition filed on behalf of concerned consumer, Holly Hykes electronically filed by Ms. Donielle M Hunter on behalf of PUCO Staff.
10/13/2016 Letter of Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. (Part 3)
10/13/2016 Letter of Notification electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. (Part 2)
10/13/2016 In the matter of the letter of Notification for the Britton-Davidson 138kV Transmission Line Project electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. (Part 1)