10/31/2019
|
Notice of the Completion of Construction of Project was May 29, 2019 electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
04/20/2017
|
Notice of Commencement of Construction electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
03/02/2017
|
Order on certificate that 16-1593-EL-BTA,16-1594-EL-BTA and 16-1595-EL-BTA be consolidated, and granting the applications filed by ATSI to amend the certificate of environmental compatibility and public need issued in the Hayes-West Fremont Case for the Hayes-West Fremont 138kV transmission line project and subject to the conditions set forth in the Hayes-West Fremont Case. |
03/02/2017
|
Service Notice |
02/27/2017
|
Notice of Hand Delivery of Staff Report of Investigation to Sandusky Public Library electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc. |
02/23/2017
|
Return mail. (unable to forward) |
10/27/2016
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
10/27/2016
|
Service Notice |
08/12/2016
|
Proof of Pub of the Public Notice of the Filing of Three Amendment Applications to the Hayes West Fremont 138kV Transmission Line Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.. |
07/29/2016
|
Letter of Notification for Amendments to the Hayes-West Fremont 138kV Transmission Line Project filed by S. Humphrys on behalf of FirstEnergy Service Company. |
07/22/2016
|
In the Matter of the Pre-Application Notification Letter, Amendment One to the Hayes-West Fremont 138 kV Transmission Line Project filed by S. Humphrys on behalf of FirstEnergy Service Company. |