12/11/2018
|
Notice In-Service Date and Construction Complete Date electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
11/13/2017
|
Notification to inform that construction of project commenced on July 10, 2017 electronically filed by Ms. Christen M. Blend on behalf of AEP Ohio Transmission Power Company, Inc. |
10/27/2016
|
Proof of Pub electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. (Morrow County) |
10/24/2016
|
Correspondence Letter accepting conditions in Staff Report electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
10/18/2016
|
Staff Report of Investigation electronically filed by Yvonne W Cooper on behalf of Staff of OPSB. |
10/12/2016
|
Letter of Notification - Supplemental electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/30/2016
|
Notification - Public Notification Compliance Filing (West Mount Vernon-Hedding) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/30/2016
|
Notification - Official Notification Compliance Filing (West Mount Vernon-Hedding) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/28/2016
|
Correspondence - Supplemental Filing (W Mt. Vernon-Hedding) electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification Part 16 of 16 Parts electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 15 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 14 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 13 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 12 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 11 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 10 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 9 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 8 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 7 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 6 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 5 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 4 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 3 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 2 electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/26/2016
|
Letter of Notification - Part 1 West Mount Vernon-Hedding 138kV Transmission Line Rebuild Project electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |
09/21/2016
|
In the Matter of the Pre-Application Notification Letter electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company. |